[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132046":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1132046,795,1,"单选题","某工程项目，建设单位未取得施工许可证便擅自开工，经查建设资金未落实。依照《建筑法》的规定，对此，正确的处理方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","责令改正，并处以罚款",false,{"key":16,"text":17,"correct":14},"B","责令改正，可以处以罚款",{"key":19,"text":20,"correct":14},"C","责令停止施工，并处以罚款",{"key":22,"text":23,"correct":24},"D","责令停止施工，可以处以罚款",true,"2007年建设工程法规真题第6题 《建筑法》规定，违反本法规定，未取得施工许可证或者开工报告未经批准擅自施工的，责令改正，对不符合开工条件的责令停止施工，可以处以罚款。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]