[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1131788":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1131788,795,2,"多选题","下列情形能够引发合同之债的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位拖欠工程进度款",true,{"key":16,"text":17,"correct":18},"B","施工中偷工减料造成的损失",false,{"key":20,"text":21,"correct":18},"C","监理单位与施工单位串通损害建设单位利益",{"key":23,"text":24,"correct":18},"D","噪声污染使周边居民无法正常休息",{"key":26,"text":27,"correct":14},"E","建材供应商供应的建筑材料不合格","AE","2013年建设工程法规真题第85题 在当事人之间因产生了合同法律关系，也就是产生了权利义务关系，便设立了债的关系。任何合同关系的设立，都会在当事人之间发生债权债务的关系。合同产生的债称为合同之债。 A项：施工合同的订立，会在施工单位和建设单位之间产生债。施工合同的业务只要是完成施工任务和支付工程款，对于支付工程款，建设单位是债务人，施工单位是债权人，所以A正确。 E项：材料设备买卖合同的订立，会在施工单位与材料设备供应商之间产生债的关系，所以E正确。 综上所述，本题正确答案为AE。@jin",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]