[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1131560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1131560,795,1,"单选题","甲施工企业与乙公司订立钢材加工合同，后因供电局无故断电，乙公司无法按时完成生产任务致使交货延迟，给甲施工企业造成了损失。关于该案责任承担的说法，正确的是（）。（2016）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","供电局向甲施工企业承担责任",false,{"key":16,"text":17,"correct":14},"B","供电局与乙公司向甲施工企业承担连带责任",{"key":19,"text":20,"correct":14},"C","乙公司可以要求供电局向甲施工企业承担责任",{"key":22,"text":23,"correct":24},"D","乙公司向甲施工企业承担责任",true,"合同之债，而且无故断电并不是不可抗力，不能免除责任 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]