[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1131378":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1131378,795,2,"多选题","关于施工许可制度和开工报告制度的说法，正确的有（）。（2016）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","实行开工报告批准制度的工程，必须符合国务院的有关规定",true,{"key":16,"text":17,"correct":14},"B","建设单位领取施工许可证后因故不能按期幵工的，最多可延期6个月",{"key":19,"text":20,"correct":14},"C","建设工程因故中止施工满一年的，恢复施工前应报发证机关核猃施工许可证",{"key":22,"text":23,"correct":24},"D","实行幵工报告批准制度的工程，幵工报告主要反映的是施工企业应具备的幵工条件",false,{"key":26,"text":27,"correct":14},"E","实行幵工报告批准制虔的工程，因故不能开工超过6个月的工程，应当重新办理幵工报告审批手续","ABCE","建设单位应当自领取施工许可证之曰起3个月内幵工。因故不能按期开工的，应当向发证机关申请延期；延其以两次为限，每次不超过3个月；中止施工满1年的工程恢复施工前，建设单位应当报发证机关核验施工许可证。 选项D,应该是反映建设单位开工的条件。",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]