[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1131233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1131233,795,1,"单选题","工程建设单位组织验收合格后投入使用，2年后外墙出现裂缝，经查是由于设计缺陷造成的，则下列说法正确的是()。（2014）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位维修，建设单位直接承担费用",true,{"key":16,"text":17,"correct":18},"B","建设单位维修并承担费用",false,{"key":20,"text":21,"correct":18},"C","施工单位维修并承担费用",{"key":23,"text":24,"correct":18},"D","施工单位维修，设计单位直接承担费用","由于设计问题造成的质量缺陷，先由施工单位负责维修，其经济责任按有关规定 通过建设单位向设计单位索赔。 26",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]