[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1131142":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1131142,795,1,"单选题","分包工程发生质量、安全、进度等问题给建设单位造成损失的，关于承担的说法，正确的是( )。（2013）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分包单位只对总承包单位负责",false,{"key":16,"text":17,"correct":14},"B","建设单位只能向给其造成损失的分包单位主张权利",{"key":19,"text":20,"correct":21},"C","总承包单位赔偿金额超过其应承担份额的，有权向有责任的分包单位追偿",true,{"key":23,"text":24,"correct":14},"D","建设单位与分布单位无合同关系，无权向分包单位主张权利","分包单位应当接受总承包单位的质量管理。总承包单位与分包单位对分包工程的质量还要依法承担连带责任。当分包工程发生质量问题时，建设单位或其他受害人既可以向分包单位请求赔偿，也可以向总承包单位请求赔偿；进行赔偿的一方有权依据分包合同的约定，对不属于自己责任的那部分赔偿向对方追偿。 5",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]