[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1131140":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1131140,795,1,"单选题","在建设单位要求赶工的情形下，隐蔽工程未通过监理单位验收，施工单位继续施工，由此发生质量问题所产生费用由( )承担。（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位",true,{"key":16,"text":17,"correct":18},"B","建设单位",false,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","建设主管部门","《建设工程质量管理条例》规定，施工单位必须建立、健全施工质量的检验制度，严格工序管理，作好隐蔽工程的质量检查和记录。隐蔽工程在隐蔽前，施工单位应当通知建设单位和建设工程质量监督机构。 所以该责任应当由施工单位承担。 6",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]