[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1131134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1131134,795,1,"单选题","施工企业在施工过程中发现工程设计图纸存在差错的，应（）。（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经建设单位同意，由施工企业负责修改",false,{"key":16,"text":17,"correct":18},"B","经建设单位同意，由设计单位负责修改",true,{"key":20,"text":21,"correct":14},"C","由施工企业负责修改，经监理单位审定",{"key":23,"text":24,"correct":14},"D","经监理单位同意，由建设单位负责修改","工程设计的修改由原设计单位负责，建筑施工企业不得擅自修改工程设计。施工单位在施工过程中发现设计文件和图纸有差错的，应当及时提出意见和建议。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]