[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1130900,795,1,"单选题","甲公司向乙公司购买50吨水泥，后甲通知乙需要更改购买数量，但一直未明确具体数量。交货期届至，乙将50吨水泥交付给甲，甲拒绝接受，理由是已告知要变更合同。关于双方合同关系的说法，正确的是( )。（2012）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","乙承担损失",false,{"key":16,"text":17,"correct":14},"B","甲可根据实际情况部分接收",{"key":19,"text":20,"correct":14},"C","双方合同已变更，乙送货构成违约",{"key":22,"text":23,"correct":24},"D","甲拒绝接收，应承担违约责任",true,"当事人协商一致，可以变更合同。法律、行政法规规定变更合同应当办理批准、登记等手续的，依照其规定。当事人对合同变更的内容约定不明确的，推定为未变更。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]