[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130751":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130751,795,2,"多选题","施工总承包单位分包工程应当经过建设单位认可，符合法律规定的认可方式有（）.（2016）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总承包合同中约定分包的内容",true,{"key":16,"text":17,"correct":18},"B","建设单位指定分包人",false,{"key":20,"text":21,"correct":14},"C","总承包合同没有约定分包内容的，事先征得建设单位同意",{"key":23,"text":24,"correct":18},"D","劳务分包合同由建设单位确认",{"key":26,"text":27,"correct":18},"E","总承包单位在建设单位推荐的分包人中选择","AC","除总承包合同中约定的分包外，必须经建设单位认可；分包工程须经建设单位认可，并不等于建设单位可以直接指定分包人，所以选项B错误； 劳务分包可以不经过建设单位确认，选项D错误； 对于建设单位推荐的分包单位，总承包单位有权作出拒绝或者采用的选择，因此选项E错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]