[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-794-8":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":610},{"id":5,"name":6,"category":7,"favorite":8},794,"一建港口与航道工程实务","建筑工程",0,8,50,1132,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,198,210,222,234,246,258,270,282,294,306,318,330,342,354,366,378,390,398,410,418,430,442,454,466,478,490,502,514,526,538,550,562,574,586,598],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":30,"analysis":33},1129705,1,"单选题","对由多层方块组成的重力式码头，在安装底层第一块方块时，方块的纵、横向两个方向都无依托，为达到安装要求，又避免因反复起落而扰动基床的整平层，一般在第一块方块的位置（ ）。",[19,23,26,29],{"key":20,"text":21,"correct":22},"A","先精安一块，以它为依托，再安其他方块",false,{"key":24,"text":25,"correct":22},"B","先粗安一块，以它为依托，再安其他方块",{"key":27,"text":28,"correct":22},"C","先粗安一块，以它为依托，再安第二块，然后以第二块为依托，按此类推，逐块安装",{"key":30,"text":31,"correct":32},"D","先粗安一块，以它为依托，再安第二块，然后以第二块为依托，重新吊安装第一块方块",true,"",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},1129706,"干地施工采用黏土回填时，填料应分层压实，每层填土虚铺厚度，对人工夯实不宜大于（ ）。",[38,40,42,44],{"key":20,"text":39,"correct":32},"0．2m",{"key":24,"text":41,"correct":22},"0．3m",{"key":27,"text":43,"correct":22},"0．4m",{"key":30,"text":45,"correct":22},"0．5m",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":24,"analysis":33},1129707,"斜坡堤砂垫层用砂宜采用（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"中细砂",{"key":24,"text":53,"correct":32},"中粗砂",{"key":27,"text":55,"correct":22},"细砂",{"key":30,"text":57,"correct":22},"砾砂",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":24,"analysis":33},1129708,"重力式码头基床抛石前，要对基槽回淤沉积物进行检查，重力密度大于（）kN／m3的回淤沉积物厚度不应大于300mm，超过时用泥泵清淤。",[62,64,66,68],{"key":20,"text":63,"correct":22},"12",{"key":24,"text":65,"correct":32},"12．6",{"key":27,"text":67,"correct":22},"13",{"key":30,"text":69,"correct":22},"13．6",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":27,"analysis":33},1129709,"当干地施工采用黏土回填时，每层填土的虚铺厚度，应按（）的规定执行。",[74,76,78,80],{"key":20,"text":75,"correct":22},"人工夯实不宜大于0．1m，机械夯实不宜大于0．2m",{"key":24,"text":77,"correct":22},"人工夯实不宜大于0．15m，机械夯实不宜大于0．3m",{"key":27,"text":79,"correct":32},"人工夯实不宜大于0．2m，机械夯实不宜大于0．4m",{"key":30,"text":81,"correct":22},"人工夯实不宜大于0．3m，机械夯实不宜大于0．5m",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":24,"analysis":33},1129710,"土工织物铺设块的铺设长度应按设计堤宽加上一定富余长度。水下铺设富余长度宜为（）m，陆上铺设富余长度宜为0．5～1.0m。",[86,88,90,92],{"key":20,"text":87,"correct":22},"1．0～2．0",{"key":24,"text":89,"correct":32},"1．5～2．5",{"key":27,"text":91,"correct":22},"2．0～3．0",{"key":30,"text":93,"correct":22},"2．5～3．5",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":24,"analysis":33},1129711,"多汊道河口拦门沙航道的整治，宜选择（）的汊道为主航道。",[98,100,102,104],{"key":20,"text":99,"correct":22},"落潮流动力较强，输沙能力较大",{"key":24,"text":101,"correct":32},"落潮流动力较强，分沙比小",{"key":27,"text":103,"correct":22},"涨潮流动力较强，输沙能力较大",{"key":30,"text":105,"correct":22},"涨落潮流动力较强，输沙能力较大",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":30,"analysis":33},1129712,"关于一般的板桩码头施工的说法，正确的是（）。",[110,112,114,116],{"key":20,"text":111,"correct":22},"导向梁距板桩墙顶的距离应小于替打套入桩的长度",{"key":24,"text":113,"correct":22},"拉杆连接铰的转动轴线应位于垂直面上",{"key":27,"text":115,"correct":22},"锚碇板（墙）的设置高程应尽量放高，以提高其承载力",{"key":30,"text":117,"correct":32},"沉桩应以桩尖设计标高作为控制标准",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":24,"analysis":33},1129713,"下列斜坡堤护面扭工字块的安放方法中，正确的是（）。",[122,124,126,128],{"key":20,"text":123,"correct":22},"自上而下安放方法",{"key":24,"text":125,"correct":32},"定点随机安放方法",{"key":27,"text":127,"correct":22},"不规则安放方法",{"key":30,"text":129,"correct":22},"随机安放方法",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":27,"analysis":33},1129714,"爆破排淤填石是在抛石体外缘一定距离和深度的淤泥质软基中埋放药包群，起爆瞬间在淤泥中形成空腔，抛石体随即坍塌充填空腔形成（ ）达到置换淤泥的目的。",[134,136,138,140],{"key":20,"text":135,"correct":22},"碎石",{"key":24,"text":137,"correct":22},"砂石",{"key":27,"text":139,"correct":32},"石舌",{"key":30,"text":141,"correct":22},"条石",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":20,"analysis":33},1129715,"重力式码头需夯实的基床要求块石的饱水抗压强度（ ）。",[146,148,150,152],{"key":20,"text":147,"correct":32},"≥50MPa",{"key":24,"text":149,"correct":22},"≥30MPa",{"key":27,"text":151,"correct":22},"≥80MPa",{"key":30,"text":153,"correct":22},"≥100MPa",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":27,"analysis":33},1129716,"重力式码头大型构件底面尺寸大于等于（ ）时，其基床可不进行极细平。",[158,160,162,164],{"key":20,"text":159,"correct":22},"10m2",{"key":24,"text":161,"correct":22},"20m2",{"key":27,"text":163,"correct":32},"30m2",{"key":30,"text":165,"correct":22},"50m2",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":20,"analysis":33},1129717,"混凝土插入式振动器的振捣顺序宜（ ），移动间距不应大于振动器有效半径的1．5倍。",[170,172,174,176],{"key":20,"text":171,"correct":32},"从近模板处开始，先外后内",{"key":24,"text":173,"correct":22},"从浇筑中心处开始，先内后外",{"key":27,"text":175,"correct":22},"从底部开始，先下后上",{"key":30,"text":177,"correct":22},"从一端向另一端",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":20,"analysis":33},1129718,"重力式码头预制沉箱采取近程拖带时，船舶一般（ ）。",[182,184,186,188],{"key":20,"text":183,"correct":32},"可用简易封舱",{"key":24,"text":185,"correct":22},"可用密封舱",{"key":27,"text":187,"correct":22},"不用封舱",{"key":30,"text":189,"correct":22},"不用密封舱",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":27,"analysis":33},1129719,"重力式码头干地填土的填料应分层压实，每层填土虚铺厚度，对机械夯实或辗压不宜大于（ ）。",[194,195,196,197],{"key":20,"text":39,"correct":22},{"key":24,"text":41,"correct":22},{"key":27,"text":43,"correct":32},{"key":30,"text":45,"correct":22},{"id":199,"libraryId":5,"type":15,"typeLabel":16,"stem":200,"options":201,"answer":27,"analysis":33},1129720,"板桩建筑物对于码头后方场地狭窄，设置锚碇结构有困难或施工期会遭受波浪作用的情况时，可采用（ ）。",[202,204,206,208],{"key":20,"text":203,"correct":22},"有锚板桩结构",{"key":24,"text":205,"correct":22},"无锚板桩结构",{"key":27,"text":207,"correct":32},"斜拉式板桩结构",{"key":30,"text":209,"correct":22},"地下墙式板桩结构",{"id":211,"libraryId":5,"type":15,"typeLabel":16,"stem":212,"options":213,"answer":30,"analysis":33},1129721,"板桩建筑物沉桩时导向梁距板墙顶的距离应（ ）替打套入桩的长度。",[214,216,218,220],{"key":20,"text":215,"correct":22},"小于",{"key":24,"text":217,"correct":22},"等于",{"key":27,"text":219,"correct":22},"略大于",{"key":30,"text":221,"correct":32},"大于",{"id":223,"libraryId":5,"type":15,"typeLabel":16,"stem":224,"options":225,"answer":24,"analysis":33},1129722,"板桩建筑物沉桩施工中，板桩偏移轴线产生平面扭转时，可（ ），使墙面平滑过渡。",[226,228,230,232],{"key":20,"text":227,"correct":22},"加异形钢板桩的方法进行调整",{"key":24,"text":229,"correct":32},"在后沉的板桩中逐根纠正",{"key":27,"text":231,"correct":22},"采用修整桩边的方法逐渐调整",{"key":30,"text":233,"correct":22},"调整打桩架的位置逐渐调整",{"id":235,"libraryId":5,"type":15,"typeLabel":16,"stem":236,"options":237,"answer":20,"analysis":33},1129723,"板桩建筑物沉桩施工中，下沉的板桩将邻近已沉的板桩“上浮”时，对“上浮”的板桩，应（ ）。",[238,240,242,244],{"key":20,"text":239,"correct":32},"复打至设计标高",{"key":24,"text":241,"correct":22},"在后续施工工序中予以调整",{"key":27,"text":243,"correct":22},"按此桩顶标高进行控制",{"key":30,"text":245,"correct":22},"重新确定后沉板桩的桩顶标高",{"id":247,"libraryId":5,"type":15,"typeLabel":16,"stem":248,"options":249,"answer":20,"analysis":33},1129724,"板桩建筑物沉桩应以（ ）作为控制标准。",[250,252,254,256],{"key":20,"text":251,"correct":32},"桩尖设计标高",{"key":24,"text":253,"correct":22},"桩顶设计标高",{"key":27,"text":255,"correct":22},"贯入度",{"key":30,"text":257,"correct":22},"锤击次数",{"id":259,"libraryId":5,"type":15,"typeLabel":16,"stem":260,"options":261,"answer":20,"analysis":33},1129725,"斜坡堤陆上土工织物铺设后，（ ）。",[262,264,266,268],{"key":20,"text":263,"correct":32},"及时覆盖，防止日晒老化",{"key":24,"text":265,"correct":22},"及时覆盖，防止风雨冲刷",{"key":27,"text":267,"correct":22},"表面涂覆，防止日晒老化",{"key":30,"text":269,"correct":22},"表面涂覆，防止风雨冲刷",{"id":271,"libraryId":5,"type":15,"typeLabel":16,"stem":272,"options":273,"answer":24,"analysis":33},1129726,"斜坡堤四脚空心方块和栅栏板护面块体的安放，其相邻块体的砌缝的最大宽度不应大于（ ）。",[274,276,278,280],{"key":20,"text":275,"correct":22},"80mm",{"key":24,"text":277,"correct":32},"100mm",{"key":27,"text":279,"correct":22},"120mm",{"key":30,"text":281,"correct":22},"150mm",{"id":283,"libraryId":5,"type":15,"typeLabel":16,"stem":284,"options":285,"answer":24,"analysis":33},1129727,"对于基岩急滩，采用切除一岸或同时切除两岸突嘴，扩大过水断面，减缓流速与比降的整治方法适用于（ ）。",[286,288,290,292],{"key":20,"text":287,"correct":22},"错口型突嘴急滩",{"key":24,"text":289,"correct":32},"对口型突嘴急滩",{"key":27,"text":291,"correct":22},"窄槽型急滩",{"key":30,"text":293,"correct":22},"潜埂型急滩",{"id":295,"libraryId":5,"type":15,"typeLabel":16,"stem":296,"options":297,"answer":30,"analysis":33},1129728,"护滩带边缘预埋压石应（ ）等，面层宜用粒径相对较大块石。",[298,300,302,304],{"key":20,"text":299,"correct":22},"粒径均匀",{"key":24,"text":301,"correct":22},"尺度规则",{"key":27,"text":303,"correct":22},"表面平整",{"key":30,"text":305,"correct":32},"级配良好",{"id":307,"libraryId":5,"type":15,"typeLabel":16,"stem":308,"options":309,"answer":20,"analysis":33},1129729,"砂枕坝体的砂枕厚度应控制在（ ）之间。",[310,312,314,316],{"key":20,"text":311,"correct":32},"400～700mm",{"key":24,"text":313,"correct":22},"400～800mm",{"key":27,"text":315,"correct":22},"500～700mm",{"key":30,"text":317,"correct":22},"500～800mm",{"id":319,"libraryId":5,"type":15,"typeLabel":16,"stem":320,"options":321,"answer":20,"analysis":33},1129730,"钢板桩护岸施工时，钢板桩宜采用拼组插入，钢板桩拼组根数（ ）。",[322,324,326,328],{"key":20,"text":323,"correct":32},"U形钢板桩宜取奇数，Z形桩宜取偶数",{"key":24,"text":325,"correct":22},"U形钢板桩和Z形桩均取偶数",{"key":27,"text":327,"correct":22},"U形钢板桩宜取偶数，Z形桩宜取奇数",{"key":30,"text":329,"correct":22},"U形钢板桩和Z形桩均取奇数",{"id":331,"libraryId":5,"type":15,"typeLabel":16,"stem":332,"options":333,"answer":27,"analysis":33},1129731,"陆上爆破的爆破层厚度超过（ ）时，应采取台阶式分层爆破。",[334,336,338,340],{"key":20,"text":335,"correct":22},"3．0m",{"key":24,"text":337,"correct":22},"4．0m",{"key":27,"text":339,"correct":32},"5．0m",{"key":30,"text":341,"correct":22},"6．0m",{"id":343,"libraryId":5,"type":15,"typeLabel":16,"stem":344,"options":345,"answer":24,"analysis":33},1129732,"（ ）是指采用水力或机械的方法为拓宽、加深水域而进行的水下土石方开挖工程。",[346,348,350,352],{"key":20,"text":347,"correct":22},"整治工程",{"key":24,"text":349,"correct":32},"疏浚工程",{"key":27,"text":351,"correct":22},"回填工程",{"key":30,"text":353,"correct":22},"港口工程",{"id":355,"libraryId":5,"type":15,"typeLabel":16,"stem":356,"options":357,"answer":27,"analysis":33},1129733,"采用链斗式挖泥船和吹泥船施工时，对于（ ）宜选用舱壁较陡的开底或开体泥驳。",[358,360,362,364],{"key":20,"text":359,"correct":22},"砂",{"key":24,"text":361,"correct":22},"粉土",{"key":27,"text":363,"correct":32},"黏性土",{"key":30,"text":365,"correct":22},"淤泥",{"id":367,"libraryId":5,"type":15,"typeLabel":16,"stem":368,"options":369,"answer":27,"analysis":33},1129734,"抓斗式挖泥船一般以（ ）来衡量其生产能力的大小。",[370,372,374,376],{"key":20,"text":371,"correct":22},"泥舱容积",{"key":24,"text":373,"correct":22},"绞刀功率",{"key":27,"text":375,"correct":32},"抓斗斗容",{"key":30,"text":377,"correct":22},"绞刀直径",{"id":379,"libraryId":5,"type":15,"typeLabel":16,"stem":380,"options":381,"answer":20,"analysis":33},1129735,"当土质稀软、泥层薄时，抓斗式挖泥船挖泥作业时（ ）。",[382,384,386,388],{"key":20,"text":383,"correct":32},"下斗间距宜大",{"key":24,"text":385,"correct":22},"增加抓斗重叠量",{"key":27,"text":387,"correct":22},"减少抓斗重叠量",{"key":30,"text":389,"correct":22},"下斗间距宜小",{"id":391,"libraryId":5,"type":15,"typeLabel":16,"stem":392,"options":393,"answer":27,"analysis":33},1129736,"抓斗式挖泥船挖掘黏土和密实砂，当抓斗充泥量不足时，应（ ）。",[394,395,396,397],{"key":20,"text":383,"correct":22},{"key":24,"text":385,"correct":22},{"key":27,"text":387,"correct":32},{"key":30,"text":389,"correct":22},{"id":399,"libraryId":5,"type":15,"typeLabel":16,"stem":400,"options":401,"answer":24,"analysis":33},1129737,"抓斗式挖泥船开挖淤泥土类时宜选用（ ）。",[402,404,406,408],{"key":20,"text":403,"correct":22},"中型抓斗",{"key":24,"text":405,"correct":32},"轻型平口抓斗",{"key":27,"text":407,"correct":22},"带齿抓斗",{"key":30,"text":409,"correct":22},"重型全齿抓斗",{"id":411,"libraryId":5,"type":15,"typeLabel":16,"stem":412,"options":413,"answer":27,"analysis":33},1129738,"抓斗式挖泥船开挖中等密实砂时宜选用（ ）。",[414,415,416,417],{"key":20,"text":407,"correct":22},{"key":24,"text":405,"correct":22},{"key":27,"text":403,"correct":32},{"key":30,"text":409,"correct":22},{"id":419,"libraryId":5,"type":15,"typeLabel":16,"stem":420,"options":421,"answer":20,"analysis":33},1129739,"吹填工程中的耙吸挖泥船自挖自吹施工方式，适用于取土区（ ）、运距远的工程。",[422,424,426,428],{"key":20,"text":423,"correct":32},"风浪大",{"key":24,"text":425,"correct":22},"风浪小",{"key":27,"text":427,"correct":22},"潮汐大",{"key":30,"text":429,"correct":22},"潮汐小",{"id":431,"libraryId":5,"type":15,"typeLabel":16,"stem":432,"options":433,"answer":27,"analysis":33},1129740,"干地施工时，必须做好基坑的防水、排水和（ ）保护。",[434,436,438,440],{"key":20,"text":435,"correct":22},"边坡",{"key":24,"text":437,"correct":22},"坡顶",{"key":27,"text":439,"correct":32},"基土",{"key":30,"text":441,"correct":22},"通道",{"id":443,"libraryId":5,"type":15,"typeLabel":16,"stem":444,"options":445,"answer":20,"analysis":33},1129741,"GPS测量应用于建立各等级的测量控制网时所采用的方法是（）处理。",[446,448,450,452],{"key":20,"text":447,"correct":32},"事后差分",{"key":24,"text":449,"correct":22},"位置差分",{"key":27,"text":451,"correct":22},"伪距差",{"key":30,"text":453,"correct":22},"载波相位差分",{"id":455,"libraryId":5,"type":15,"typeLabel":16,"stem":456,"options":457,"answer":30,"analysis":33},1129742,"海水环境中有掩护港口与航道工程混凝土的水位变动区是指（）。",[458,460,462,464],{"key":20,"text":459,"correct":22},"设计高水位至设计低水位间的区域",{"key":24,"text":461,"correct":22},"设计高水位至设计低水位减1.0m间的区域",{"key":27,"text":463,"correct":22},"设计高水位减1.0m至设计低水位间的区域",{"key":30,"text":465,"correct":32},"设计高水位减1.0m至设计低水位减1.0m间的区域",{"id":467,"libraryId":5,"type":15,"typeLabel":16,"stem":468,"options":469,"answer":20,"analysis":33},1129743,"有抗冻要求的港口与航道工程C40级以上混凝土粗骨料中总含泥量的限制值为粗骨料质量的（）。",[470,472,474,476],{"key":20,"text":471,"correct":32},"≤0．5％",{"key":24,"text":473,"correct":22},"≤0．7％",{"key":27,"text":475,"correct":22},"≤1．0％",{"key":30,"text":477,"correct":22},"≤2．0％",{"id":479,"libraryId":5,"type":15,"typeLabel":16,"stem":480,"options":481,"answer":20,"analysis":33},1129744,"海水环境港口与航道工程混凝土配合比设计中，按耐久性要求，对（）有最小值的限制。",[482,484,486,488],{"key":20,"text":483,"correct":32},"胶凝材料用量",{"key":24,"text":485,"correct":22},"用水量",{"key":27,"text":487,"correct":22},"水胶比",{"key":30,"text":489,"correct":22},"细骨料用量",{"id":491,"libraryId":5,"type":15,"typeLabel":16,"stem":492,"options":493,"answer":20,"analysis":33},1129745,"《水运工程混凝土质量控制标准》JTS 202—2—2011中对海水环境钢筋混凝土的保护层最小厚度作了具体规定。混凝土保护层厚度是指（）。",[494,496,498,500],{"key":20,"text":495,"correct":32},"主筋表面与混凝土表面的最小距离",{"key":24,"text":497,"correct":22},"箍筋表面与混凝土表面的最小距离",{"key":27,"text":499,"correct":22},"主筋中心与混凝土表面的距离",{"key":30,"text":501,"correct":22},"箍筋中心与混凝土表面的距离",{"id":503,"libraryId":5,"type":15,"typeLabel":16,"stem":504,"options":505,"answer":30,"analysis":33},1129746,"真空预压法的施工检测与效果检验，应测量泵上及膜下真空度，并应在真空预压加固区（）埋设测斜仪，测量土体的侧向位移。",[506,508,510,512],{"key":20,"text":507,"correct":22},"中心",{"key":24,"text":509,"correct":22},"中心及边缘处",{"key":27,"text":511,"correct":22},"中心与边缘处之间",{"key":30,"text":513,"correct":32},"边缘处",{"id":515,"libraryId":5,"type":15,"typeLabel":16,"stem":516,"options":517,"answer":24,"analysis":33},1129747,"在海港工程中，采用涂层保护工艺的钢管桩，其涂层应伸入桩帽（或横梁）混凝土内（）。",[518,520,522,524],{"key":20,"text":519,"correct":22},"0～50mm",{"key":24,"text":521,"correct":32},"50～100mm",{"key":27,"text":523,"correct":22},"100～150mm",{"key":30,"text":525,"correct":22},"150～200mm",{"id":527,"libraryId":5,"type":15,"typeLabel":16,"stem":528,"options":529,"answer":30,"analysis":33},1129748,"不正规半日潮混合潮在一个太阴日中有（ ）。",[530,532,534,536],{"key":20,"text":531,"correct":22},"一次高潮和两次低潮",{"key":24,"text":533,"correct":22},"两次高潮和一次低潮",{"key":27,"text":535,"correct":22},"两次高潮和两次低潮，两次相邻的高潮或低潮的潮高几乎相等",{"key":30,"text":537,"correct":32},"两次高潮和两次低潮，两次相邻的高潮或低潮的潮高不相等",{"id":539,"libraryId":5,"type":15,"typeLabel":16,"stem":540,"options":541,"answer":30,"analysis":33},1129749,"在淤泥质海岸，（ ）是输沙的主要动力。",[542,544,546,548],{"key":20,"text":543,"correct":22},"船舶航行",{"key":24,"text":545,"correct":22},"水下挖泥",{"key":27,"text":547,"correct":22},"波浪",{"key":30,"text":549,"correct":32},"潮流",{"id":551,"libraryId":5,"type":15,"typeLabel":16,"stem":552,"options":553,"answer":24,"analysis":33},1129750,"河床上固体颗粒上升和下降均取决于接近河床表面处的（ ）的变化。",[554,556,558,560],{"key":20,"text":555,"correct":22},"水平速度",{"key":24,"text":557,"correct":32},"垂直分速",{"key":27,"text":559,"correct":22},"颗粒大小",{"key":30,"text":561,"correct":22},"颗粒黏度",{"id":563,"libraryId":5,"type":15,"typeLabel":16,"stem":564,"options":565,"answer":24,"analysis":33},1129751,"风速为（ ）或风力6级的风称为强风。",[566,568,570,572],{"key":20,"text":567,"correct":22},"8．0～10．7m／s",{"key":24,"text":569,"correct":32},"10．8～13．8m／s",{"key":27,"text":571,"correct":22},"13．9～17．1m／s",{"key":30,"text":573,"correct":22},"17．2～20．7m／s",{"id":575,"libraryId":5,"type":15,"typeLabel":16,"stem":576,"options":577,"answer":27,"analysis":33},1129752,"大中型工程的地质勘察可分为（ ）三个阶段。",[578,580,582,584],{"key":20,"text":579,"correct":22},"预可行性研究阶段勘察、初步设计阶段勘察、施工图设计阶段勘察",{"key":24,"text":581,"correct":22},"可行性研究阶段勘察、技术设计阶段勘察、施工图设计阶段勘察",{"key":27,"text":583,"correct":32},"可行性研究阶段勘察、初步设计阶段勘察、施工图设计阶段勘察",{"key":30,"text":585,"correct":22},"立项报告研究阶段勘察、初步设计阶段勘察、施工图设计阶段勘察",{"id":587,"libraryId":5,"type":15,"typeLabel":16,"stem":588,"options":589,"answer":24,"analysis":33},1129753,"利用经纬仪等各种测量仪器将地球表面各点的位置、高度以及各种地物（河流、森林及道路、桥梁、房屋）的位置和形状测出，并按一定比例尺和规定的符号，绘在图纸上，形成（ ）。",[590,592,594,596],{"key":20,"text":591,"correct":22},"平面图",{"key":24,"text":593,"correct":32},"地形图",{"key":27,"text":595,"correct":22},"水深图",{"key":30,"text":597,"correct":22},"海图",{"id":599,"libraryId":5,"type":15,"typeLabel":16,"stem":600,"options":601,"answer":24,"analysis":33},1129754,"地形图测图比例尺应根据测量类别、测区范围等按有关规范规定选用，施工测量的水工建筑物及附属设施测图比例尺为（ ）。",[602,604,606,608],{"key":20,"text":603,"correct":22},"1：100～1：1000",{"key":24,"text":605,"correct":32},"1：200～1：2000",{"key":27,"text":607,"correct":22},"1：300～1：2000",{"key":30,"text":609,"correct":22},"1：500～1：2000",[611,614,617,620,623,626],{"id":15,"name":612,"category":7,"favorite":613},"领导干部任职前廉政法规知识测试题",92,{"id":615,"name":616,"category":7,"favorite":15},595,"建筑结构与设备",{"id":618,"name":619,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":621,"name":622,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":624,"name":625,"category":7,"favorite":8},534,"BIM工程师",{"id":627,"name":625,"category":7,"favorite":8},535]