[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-794-2":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":611},{"id":5,"name":6,"category":7,"favorite":8},794,"一建港口与航道工程实务","建筑工程",0,2,50,1132,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,202,214,226,238,250,259,269,280,292,302,314,326,338,350,359,371,383,395,407,419,431,443,455,467,479,491,503,515,527,539,551,563,575,587,599],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":30,"analysis":33},1129191,1,"单选题","高桩码头岸坡回填时，高桩基处的回填应（ ）。",[19,23,26,29],{"key":20,"text":21,"correct":22},"A","先回填水侧",false,{"key":24,"text":25,"correct":22},"B","先回填陆侧",{"key":27,"text":28,"correct":22},"C","水陆两侧对称回填",{"key":30,"text":31,"correct":32},"D","沿桩周对称回填",true,"",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":27,"analysis":33},1129192,"板桩码头建筑物在岸坡上沉桩时，应控制（ ），对邻近岸坡和建筑物进行监控，如发现异常现象，应及时研究处理。",[38,40,42,44],{"key":20,"text":39,"correct":22},"桩的偏位",{"key":24,"text":41,"correct":22},"沉桩数量",{"key":27,"text":43,"correct":32},"沉桩速率",{"key":30,"text":45,"correct":22},"桩的倾斜",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":24,"analysis":33},1129193,"板桩建筑物沉桩中，沿板桩墙纵轴线方向的垂直度偏差超过规定时，对于钢板桩，可采用（ ）的方法进行调整。",[50,52,54,56],{"key":20,"text":51,"correct":22},"调整桩尖斜度",{"key":24,"text":53,"correct":32},"加楔形板桩",{"key":27,"text":55,"correct":22},"调整打桩架的侧向斜度",{"key":30,"text":57,"correct":22},"调整导向架",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":20,"analysis":33},1129194,"板桩建筑物沉桩施工中，下沉的板桩将邻近已沉的板桩“带下”时，可根据“带下”的情况（ ）。",[62,64,66,68],{"key":20,"text":63,"correct":32},"重新确定后沉板桩的桩顶标高",{"key":24,"text":65,"correct":22},"在后续施工工序中予以调整",{"key":27,"text":67,"correct":22},"其他桩顶标高均按此进行调整",{"key":30,"text":69,"correct":22},"重新确定板桩桩顶的控制标高",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":27,"analysis":33},1129195,"板桩沉桩时，打桩方法一般采用锤击法，为提高打桩效率和避免打坏桩头，宜采用（ ）。",[74,76,78,80],{"key":20,"text":75,"correct":22},"小锤“轻锤轻打”",{"key":24,"text":77,"correct":22},"小锤“轻锤重打”",{"key":27,"text":79,"correct":32},"大锤“重锤轻打”",{"key":30,"text":81,"correct":22},"大锤“重锤重打”",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":20,"analysis":33},1129197,"板桩建筑物锚碇板（墙）是靠（ ）来平衡拉杆拉力。",[86,88,90,92],{"key":20,"text":87,"correct":32},"墙前面的土抗力",{"key":24,"text":89,"correct":22},"墙后面的土抗力",{"key":27,"text":91,"correct":22},"锚碇板（墙）自重",{"key":30,"text":93,"correct":22},"锚碇板（墙）和土的重量组成的抗力",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":27,"analysis":33},1129198,"板桩建筑物锚碇板（墙）的设置高程，在施工条件允许的情况下，应（ ），以提高其承载能力。",[98,100,102,104],{"key":20,"text":99,"correct":22},"尽量放高",{"key":24,"text":101,"correct":22},"尽量在施工水位",{"key":27,"text":103,"correct":32},"尽量放低",{"key":30,"text":105,"correct":22},"尽量在设计低水位",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":24,"analysis":33},1129199,"板桩建筑物的锚碇桩（板桩）是依靠其在土中的（ ）作用来承受拉杆的拉力。",[110,112,114,116],{"key":20,"text":111,"correct":22},"摩擦阻力",{"key":24,"text":113,"correct":32},"弹性嵌固",{"key":27,"text":115,"correct":22},"地基支承",{"key":30,"text":117,"correct":22},"嵌固和摩阻",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":30,"analysis":33},1129200,"板桩建筑物锚碇系统拉杆的安装，拉杆连接铰的转动轴线应位于（ ）。",[122,124,126,128],{"key":20,"text":123,"correct":22},"垂直面上",{"key":24,"text":125,"correct":22},"向海侧倾斜面上",{"key":27,"text":127,"correct":22},"向陆侧倾斜面上",{"key":30,"text":129,"correct":32},"水平面上",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":27,"analysis":33},1129201,"板桩建筑物锚碇系统拉杆安装时，如设计对拉杆的安装支垫无具体规定时，可将拉杆搁置在垫平的垫块上，垫块的间距取（ ）m左右。",[134,136,138,140],{"key":20,"text":135,"correct":22},"3",{"key":24,"text":137,"correct":22},"4",{"key":27,"text":139,"correct":32},"5",{"key":30,"text":141,"correct":22},"6",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":24,"analysis":33},1129202,"砂垫层抛填时，应考虑水深、水流和波浪等自然条件对砂粒产生漂流的影响，抛砂应（ ）施工。",[146,148,150,152],{"key":20,"text":147,"correct":22},"分层",{"key":24,"text":149,"correct":32},"分段",{"key":27,"text":151,"correct":22},"分区",{"key":30,"text":153,"correct":22},"分条",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":27,"analysis":33},1129203,"水下铺设土工织物垫层时，在潮流较大区域宜在（ ）施工。",[158,160,162,164],{"key":20,"text":159,"correct":22},"低潮时",{"key":24,"text":161,"correct":22},"落潮时",{"key":27,"text":163,"correct":32},"平潮时",{"key":30,"text":165,"correct":22},"高潮时",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":27,"analysis":33},1129205,"斜坡堤软土地基上的抛石，当有挤淤要求时，应从（ ）。",[170,172,174,176],{"key":20,"text":171,"correct":22},"断面两侧逐渐向中间抛填",{"key":24,"text":173,"correct":22},"堤的端头由两侧逐渐向中间抛填",{"key":27,"text":175,"correct":32},"断面中间逐渐向两侧抛填",{"key":30,"text":177,"correct":22},"堤的端头由中间逐渐向两侧抛填",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":30,"analysis":33},1129206,"对于后浇带混凝土施工的要求，当设计未作规定时，应滞后于后浇带两侧混凝土的浇筑时间不少于（ ）。",[182,184,186,188],{"key":20,"text":183,"correct":22},"7d",{"key":24,"text":185,"correct":22},"14d",{"key":27,"text":187,"correct":22},"21d",{"key":30,"text":189,"correct":32},"30d",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":27,"analysis":33},1129207,"大幅土工膜拼接，以采用胶接法粘合或热元件法焊接，胶接法搭接宽度和热元件法焊接叠合宽度分别宜为（ ）。",[194,196,198,200],{"key":20,"text":195,"correct":22},"40～60mm和10～15mm",{"key":24,"text":197,"correct":22},"40～60mm和30～40mm",{"key":27,"text":199,"correct":32},"50～70mm和10～15mm",{"key":30,"text":201,"correct":22},"50～70mm和30～40mm",{"id":203,"libraryId":5,"type":15,"typeLabel":16,"stem":204,"options":205,"answer":20,"analysis":33},1129208,"当引航道采用模袋混凝土护面，其表面平整度允许偏差为（ ）。",[206,208,210,212],{"key":20,"text":207,"correct":32},"陆上不应大于100mm，水下不应大于150mm",{"key":24,"text":209,"correct":22},"陆上不应大于150mm，水下不应大于150mm",{"key":27,"text":211,"correct":22},"陆上不应大于100mm，水下不应大于200mm",{"key":30,"text":213,"correct":22},"陆上不应大于150mm，水下不应大于200mm",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":24,"analysis":33},1129209,"对于沙质浅滩，固定和加高边滩，调整航道流速，集中水流冲刷航槽的整治方法适用于（ ）。",[218,220,222,224],{"key":20,"text":219,"correct":22},"弯道浅滩",{"key":24,"text":221,"correct":32},"过渡段浅滩",{"key":27,"text":223,"correct":22},"汊道浅滩",{"key":30,"text":225,"correct":22},"散乱浅滩",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":20,"analysis":33},1129212,"采用清礁措施，扩大过水断面，枯水急滩在下游有条件筑坝时可筑坝壅水，减缓滩口流速和比降的整治方法适用于（ ）。",[230,232,234,236],{"key":20,"text":231,"correct":32},"窄槽型急滩",{"key":24,"text":233,"correct":22},"对口型突嘴急滩",{"key":27,"text":235,"correct":22},"错口型突嘴急滩",{"key":30,"text":237,"correct":22},"多个突嘴相临近的急滩",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":27,"analysis":33},1129213,"（ ）适用于单一河道中急弯险滩的整治。",[242,244,246,248],{"key":20,"text":243,"correct":22},"在凹岸建顺坝或丁坝",{"key":24,"text":245,"correct":22},"炸除礁石",{"key":27,"text":247,"correct":32},"在突嘴上游建丁坝",{"key":30,"text":249,"correct":22},"废弃老槽、另辟新槽",{"id":251,"libraryId":5,"type":15,"typeLabel":16,"stem":252,"options":253,"answer":30,"analysis":33},1129214,"（ ）适用于分汊河道内急弯险滩的整治。",[254,256,257,258],{"key":20,"text":255,"correct":22},"炸除石梁",{"key":24,"text":245,"correct":22},{"key":27,"text":247,"correct":22},{"key":30,"text":249,"correct":32},{"id":260,"libraryId":5,"type":15,"typeLabel":16,"stem":261,"options":262,"answer":24,"analysis":33},1129215,"凹岸突出岩嘴形成的泡漩险滩，可根据河道宽窄情况，可采用（ ）的措施整治。",[263,265,267,268],{"key":20,"text":264,"correct":22},"在凹岸建顺坝",{"key":24,"text":266,"correct":32},"在岩嘴上游建潜坝",{"key":27,"text":247,"correct":22},{"key":30,"text":243,"correct":22},{"id":270,"libraryId":5,"type":15,"typeLabel":16,"stem":271,"options":272,"answer":20,"analysis":33},1129216,"河心礁石或岸边突出石梁形成的泡漩险滩，可采用（ ）的措施整治。",[273,275,277,278],{"key":20,"text":274,"correct":32},"炸除礁石或石梁",{"key":24,"text":276,"correct":22},"在岩嘴上游建丁坝",{"key":27,"text":247,"correct":22},{"key":30,"text":279,"correct":22},"建洲头顺坝",{"id":281,"libraryId":5,"type":15,"typeLabel":16,"stem":282,"options":283,"answer":20,"analysis":33},1129218,"土工织物软体排护底沉排过程中出现排体撕裂的，排体着床的实际最小搭接长度不得小于（ ）。",[284,286,288,290],{"key":20,"text":285,"correct":32},"6．0m",{"key":24,"text":287,"correct":22},"7．0m",{"key":27,"text":289,"correct":22},"8．0m",{"key":30,"text":291,"correct":22},"9．0m",{"id":293,"libraryId":5,"type":15,"typeLabel":16,"stem":294,"options":295,"answer":27,"analysis":33},1129219,"土工织物软体排护底排体沉放过程中，当施工区水深大于（ ）时，沉排前宜通过试验确定排体足够搭接宽度的预留量。",[296,297,298,300],{"key":20,"text":285,"correct":22},{"key":24,"text":289,"correct":22},{"key":27,"text":299,"correct":32},"10．0m",{"key":30,"text":301,"correct":22},"12．0m",{"id":303,"libraryId":5,"type":15,"typeLabel":16,"stem":304,"options":305,"answer":20,"analysis":33},1129222,"吹填工程是指将挖泥船挖取的泥沙，通过（ ）输送到指定地点进行填筑的作业。",[306,308,310,312],{"key":20,"text":307,"correct":32},"排泥管线",{"key":24,"text":309,"correct":22},"外抛",{"key":27,"text":311,"correct":22},"回填",{"key":30,"text":313,"correct":22},"干砌",{"id":315,"libraryId":5,"type":15,"typeLabel":16,"stem":316,"options":317,"answer":24,"analysis":33},1129227,"耙吸船开挖淤泥质土对地航速宜采用（ ）。",[318,320,322,324],{"key":20,"text":319,"correct":22},"0．5～1kn",{"key":24,"text":321,"correct":32},"2～2．5kn",{"key":27,"text":323,"correct":22},"3～4kn",{"key":30,"text":325,"correct":22},"5～6kn",{"id":327,"libraryId":5,"type":15,"typeLabel":16,"stem":328,"options":329,"answer":24,"analysis":33},1129229,"耙吸挖泥船挖掘较硬土质时，波浪补偿器压力应调（ ）。",[330,332,334,336],{"key":20,"text":331,"correct":22},"高",{"key":24,"text":333,"correct":32},"低",{"key":27,"text":335,"correct":22},"无关",{"key":30,"text":337,"correct":22},"均可",{"id":339,"libraryId":5,"type":15,"typeLabel":16,"stem":340,"options":341,"answer":20,"analysis":33},1129230,"耙吸挖泥船开挖松散和中等密实砂宜选用的耙头是（ ）。",[342,344,346,348],{"key":20,"text":343,"correct":32},"冲刷型耙头",{"key":24,"text":345,"correct":22},"挖掘型耙头",{"key":27,"text":347,"correct":22},"吸人型耙头",{"key":30,"text":349,"correct":22},"主动挖掘型耙头",{"id":351,"libraryId":5,"type":15,"typeLabel":16,"stem":352,"options":353,"answer":24,"analysis":33},1129231,"闸室、闸首和输水廊道等混凝土结构分层浇筑时，上下层与相邻段混凝凝土浇筑的时间间隔不宜超过（ ）。",[354,355,356,357],{"key":20,"text":183,"correct":22},{"key":24,"text":185,"correct":32},{"key":27,"text":187,"correct":22},{"key":30,"text":358,"correct":22},"28d",{"id":360,"libraryId":5,"type":15,"typeLabel":16,"stem":361,"options":362,"answer":20,"analysis":33},1129232,"采用整治与疏浚相结合的方法，扩大滩口过水断面，调整滩口河床形态的整治方法适用于（ ）。",[363,365,367,369],{"key":20,"text":364,"correct":32},"卵石急滩",{"key":24,"text":366,"correct":22},"溪口急滩",{"key":27,"text":368,"correct":22},"崩岩急滩",{"key":30,"text":370,"correct":22},"滑坡急滩",{"id":372,"libraryId":5,"type":15,"typeLabel":16,"stem":373,"options":374,"answer":24,"analysis":33},1129234,"重力式码头胸墙混凝土直接在填料上浇筑时，应在（ ）浇筑。",[375,377,379,381],{"key":20,"text":376,"correct":22},"填筑后",{"key":24,"text":378,"correct":32},"填筑密实后",{"key":27,"text":380,"correct":22},"填筑密实三个月以后",{"key":30,"text":382,"correct":22},"填筑密实六个月以后",{"id":384,"libraryId":5,"type":15,"typeLabel":16,"stem":385,"options":386,"answer":27,"analysis":33},1129235,"爆破开挖水下岩石基槽，浅点处整平层的厚度不应小于（ ）。",[387,389,391,393],{"key":20,"text":388,"correct":22},"0．1m",{"key":24,"text":390,"correct":22},"0．2m",{"key":27,"text":392,"correct":32},"0．3m",{"key":30,"text":394,"correct":22},"0．5m",{"id":396,"libraryId":5,"type":15,"typeLabel":16,"stem":397,"options":398,"answer":24,"analysis":33},1129238,"基床夯实后，进行复夯检验时，复打一夯次的平均沉降量应不大于（ ）。",[399,401,403,405],{"key":20,"text":400,"correct":22},"10mm",{"key":24,"text":402,"correct":32},"30mm",{"key":27,"text":404,"correct":22},"50mm",{"key":30,"text":406,"correct":22},"300mm",{"id":408,"libraryId":5,"type":15,"typeLabel":16,"stem":409,"options":410,"answer":27,"analysis":33},1129239,"局部补抛石层平均厚度大于50cm时，应按原设计药量的（ ）补爆一次，补爆范围内的药包应按原设计位置布放。",[411,413,415,417],{"key":20,"text":412,"correct":22},"1／4",{"key":24,"text":414,"correct":22},"1／3",{"key":27,"text":416,"correct":32},"1／2",{"key":30,"text":418,"correct":22},"1倍",{"id":420,"libraryId":5,"type":15,"typeLabel":16,"stem":421,"options":422,"answer":27,"analysis":33},1129240,"进行水下抛石基床整平时，对于块石间不平整部分，宜用（ ）填充。",[423,425,427,429],{"key":20,"text":424,"correct":22},"5～50mm碎石",{"key":24,"text":426,"correct":22},"30～70mm碎石",{"key":27,"text":428,"correct":32},"二片石",{"key":30,"text":430,"correct":22},"混合石",{"id":432,"libraryId":5,"type":15,"typeLabel":16,"stem":433,"options":434,"answer":27,"analysis":33},1129242,"重力式码头预制沉箱浮在水上接高时，必须及时（ ）以保证沉箱的浮运稳定。",[435,437,439,441],{"key":20,"text":436,"correct":22},"向箱舱加水",{"key":24,"text":438,"correct":22},"从箱舱抽水",{"key":27,"text":440,"correct":32},"调整压载",{"key":30,"text":442,"correct":22},"装模浇筑",{"id":444,"libraryId":5,"type":15,"typeLabel":16,"stem":445,"options":446,"answer":24,"analysis":33},1129243,"重力式码头预制沉箱采取远程拖带时，宜采取（ ）措施。",[447,449,451,453],{"key":20,"text":448,"correct":22},"简易封舱",{"key":24,"text":450,"correct":32},"密封舱",{"key":27,"text":452,"correct":22},"不用封舱",{"key":30,"text":454,"correct":22},"不用密封舱",{"id":456,"libraryId":5,"type":15,"typeLabel":16,"stem":457,"options":458,"answer":27,"analysis":33},1129245,"如重力式码头所在地波浪、水流条件复杂，在沉箱安放后，应立即将箱内灌水，待经历（ ）后，复测位置，确认符合质量标准后，及时填充箱内填料。",[459,461,463,465],{"key":20,"text":460,"correct":22},"1～2个高潮",{"key":24,"text":462,"correct":22},"2～3个高潮",{"key":27,"text":464,"correct":32},"1～2个低潮",{"key":30,"text":466,"correct":22},"2～3个低潮",{"id":468,"libraryId":5,"type":15,"typeLabel":16,"stem":469,"options":470,"answer":20,"analysis":33},1129246,"重力式码头在向沉箱内抽水或回填时，同一沉箱的各舱宜（ ）进行，其舱面高差限值，通过验算确定。",[471,473,475,477],{"key":20,"text":472,"correct":32},"同步",{"key":24,"text":474,"correct":22},"对角",{"key":27,"text":476,"correct":22},"左右",{"key":30,"text":478,"correct":22},"对称",{"id":480,"libraryId":5,"type":15,"typeLabel":16,"stem":481,"options":482,"answer":30,"analysis":33},1129247,"重力式码头扶壁混凝土构件的运输一般采用方驳。为防止在装卸时方驳发生横倾，扶壁的肋应（ ）于方驳的纵轴线，且扶壁的重心应位于方驳的纵轴线上。",[483,485,487,489],{"key":20,"text":484,"correct":22},"垂直",{"key":24,"text":486,"correct":22},"呈30°角",{"key":27,"text":488,"correct":22},"呈45°角",{"key":30,"text":490,"correct":32},"平行",{"id":492,"libraryId":5,"type":15,"typeLabel":16,"stem":493,"options":494,"answer":20,"analysis":33},1129248,"沉箱安放时的灌水、抽水、回填料，同一沉箱的各舱格应（ ）进行。",[495,497,499,501],{"key":20,"text":496,"correct":32},"同步进行",{"key":24,"text":498,"correct":22},"跳舱进行",{"key":27,"text":500,"correct":22},"逐舱进行",{"key":30,"text":502,"correct":22},"按对称舱格进行",{"id":504,"libraryId":5,"type":15,"typeLabel":16,"stem":505,"options":506,"answer":24,"analysis":33},1129249,"拖运沉箱时，在正常航速下其曳引作用点在定倾中心以下（ ）左右时最稳定。",[507,509,511,513],{"key":20,"text":508,"correct":22},"在定倾中心点上",{"key":24,"text":510,"correct":32},"10cm",{"key":27,"text":512,"correct":22},"30cm",{"key":30,"text":514,"correct":22},"20cm",{"id":516,"libraryId":5,"type":15,"typeLabel":16,"stem":517,"options":518,"answer":24,"analysis":33},1129250,"重力式方块码头抛填棱体的制作可在方块安装完（ ）后开始。",[519,521,523,525],{"key":20,"text":520,"correct":22},"1层",{"key":24,"text":522,"correct":32},"1～2层",{"key":27,"text":524,"correct":22},"2～3层",{"key":30,"text":526,"correct":22},"1～3层",{"id":528,"libraryId":5,"type":15,"typeLabel":16,"stem":529,"options":530,"answer":24,"analysis":33},1129251,"高桩码头在（ ）中沉桩，以标高控制为主，贯入度可作校核。",[531,533,535,537],{"key":20,"text":532,"correct":22},"砂性土层",{"key":24,"text":534,"correct":32},"黏性土",{"key":27,"text":536,"correct":22},"风化岩层",{"key":30,"text":538,"correct":22},"淤泥土",{"id":540,"libraryId":5,"type":15,"typeLabel":16,"stem":541,"options":542,"answer":30,"analysis":33},1129252,"高桩码头桩裂损的控制，除了控制制造和起吊桩的质量外，就是要采取措施控制（ ）。",[543,545,547,549],{"key":20,"text":544,"correct":22},"桩的自身强度",{"key":24,"text":546,"correct":22},"沉桩周边环境",{"key":27,"text":548,"correct":22},"沉桩施工条件",{"key":30,"text":550,"correct":32},"打桩应力",{"id":552,"libraryId":5,"type":15,"typeLabel":16,"stem":553,"options":554,"answer":30,"analysis":33},1129253,"港口与航道工程中桩基工程中的沉桩结束后应及时（ ），加强基桩之间的连接，以减少桩身位移，改善施工期受力状态。",[555,557,559,561],{"key":20,"text":556,"correct":22},"拉桩",{"key":24,"text":558,"correct":22},"浇筑桩帽",{"key":27,"text":560,"correct":22},"上部施工",{"key":30,"text":562,"correct":32},"夹桩",{"id":564,"libraryId":5,"type":15,"typeLabel":16,"stem":565,"options":566,"answer":30,"analysis":33},1129254,"高桩码头在斜坡上打桩时，为保证桩位符合设计要求和防止岸坡滑动，应采取（ ）的方法。",[567,569,571,573],{"key":20,"text":568,"correct":22},"严格按设计桩位下桩",{"key":24,"text":570,"correct":22},"严格按设计桩位下桩并削坡",{"key":27,"text":572,"correct":22},"恰当偏离桩位按顺序沉桩",{"key":30,"text":574,"correct":32},"恰当偏离桩位，削坡并分区跳打",{"id":576,"libraryId":5,"type":15,"typeLabel":16,"stem":577,"options":578,"answer":27,"analysis":33},1129255,"高桩码头预制构件吊运时的混凝土强度应（ ）。如需提前吊运，应经验算。",[579,581,583,585],{"key":20,"text":580,"correct":22},"达设计强度的50％",{"key":24,"text":582,"correct":22},"达设计强度的70％",{"key":27,"text":584,"correct":32},"符合设计要求",{"key":30,"text":586,"correct":22},"达设计强度",{"id":588,"libraryId":5,"type":15,"typeLabel":16,"stem":589,"options":590,"answer":27,"analysis":33},1129257,"高桩码头预制构件吊运时应使各吊点同时受力，并应注意防止构件产生扭曲。吊绳与构件水平面的夹角（ ）。",[591,593,595,597],{"key":20,"text":592,"correct":22},"不应大于45°",{"key":24,"text":594,"correct":22},"不应大于60°",{"key":27,"text":596,"correct":32},"不应小于45°",{"key":30,"text":598,"correct":22},"不应小于60°",{"id":600,"libraryId":5,"type":15,"typeLabel":16,"stem":601,"options":602,"answer":30,"analysis":33},1129258,"高桩码头预制构件存放按三点以上受力状态设计的预制构件，宜采用（ ）支垫存放。垫木应均匀铺设，并应注意场地不均匀沉降对构件的影响。",[603,605,607,609],{"key":20,"text":604,"correct":22},"两点",{"key":24,"text":606,"correct":22},"五点",{"key":27,"text":608,"correct":22},"三点",{"key":30,"text":610,"correct":32},"多点",[612,615,618,621,624,627],{"id":15,"name":613,"category":7,"favorite":614},"领导干部任职前廉政法规知识测试题",92,{"id":616,"name":617,"category":7,"favorite":15},595,"建筑结构与设备",{"id":619,"name":620,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":622,"name":623,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":625,"name":626,"category":7,"favorite":8},534,"BIM工程师",{"id":628,"name":626,"category":7,"favorite":8},535]