[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-794-17":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":731},{"id":5,"name":6,"category":7,"favorite":8},794,"一建港口与航道工程实务","建筑工程",0,17,50,1132,[13,38,53,67,82,97,112,126,137,150,165,180,195,210,225,239,254,268,282,296,310,325,340,354,369,383,397,411,425,439,454,468,482,496,510,525,539,553,565,576,590,604,617,631,645,659,673,688,703,717],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},1130341,2,"多选题","疏浚工程中属于施工自然条件的是（ ）。",[19,23,26,29,33],{"key":20,"text":21,"correct":22},"A","水文",true,{"key":24,"text":25,"correct":22},"B","气象",{"key":27,"text":28,"correct":22},"C","工程地质",{"key":30,"text":31,"correct":32},"D","交通",false,{"key":34,"text":35,"correct":32},"E","补给","ABC","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},1130345,"内河航运工程建设项目总概算中其他费用包括（ ）等费用。",[42,44,46,48,50],{"key":20,"text":43,"correct":22},"联合试运转费",{"key":24,"text":45,"correct":22},"生产职工培训费",{"key":27,"text":47,"correct":32},"扫海费",{"key":30,"text":49,"correct":32},"实船停滞费",{"key":34,"text":51,"correct":22},"航道整治效果观察费","ABE",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":66,"analysis":37},1130346,"疏浚工程预算工程费中间接费应包括（ ）。",[57,59,61,63,64],{"key":20,"text":58,"correct":32},"专项费用",{"key":24,"text":60,"correct":22},"企业管理费",{"key":27,"text":62,"correct":22},"财务费用",{"key":30,"text":47,"correct":32},{"key":34,"text":65,"correct":32},"调遣费","BC",{"id":68,"libraryId":5,"type":15,"typeLabel":16,"stem":69,"options":70,"answer":81,"analysis":37},1130347,"水运工程单位工程概、预算费用包括（ ）等。",[71,73,75,77,79],{"key":20,"text":72,"correct":22},"直接费",{"key":24,"text":74,"correct":32},"现场管理费",{"key":27,"text":76,"correct":22},"利润",{"key":30,"text":78,"correct":32},"临时施工费",{"key":34,"text":80,"correct":32},"现场经费","AC",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":96,"analysis":37},1130348,"沿海港口建设项目的总概算构成包括（ ）等费用。",[86,88,90,92,94],{"key":20,"text":87,"correct":22},"工程费用",{"key":24,"text":89,"correct":22},"其他费用",{"key":27,"text":91,"correct":22},"预留费用",{"key":30,"text":93,"correct":22},"建设期贷款利息",{"key":34,"text":95,"correct":32},"供电贴费","ABCD",{"id":98,"libraryId":5,"type":15,"typeLabel":16,"stem":99,"options":100,"answer":111,"analysis":37},1130349,"沿海港口建设项目总概算中的工程费用包括（ ）。",[101,103,105,107,109],{"key":20,"text":102,"correct":22},"建筑工程费",{"key":24,"text":104,"correct":32},"办公和生活家具购置费",{"key":27,"text":106,"correct":22},"安装工程费",{"key":30,"text":108,"correct":32},"工器具及生产家具购置费",{"key":34,"text":110,"correct":22},"设备购置费","ACE",{"id":113,"libraryId":5,"type":15,"typeLabel":16,"stem":114,"options":115,"answer":36,"analysis":37},1130350,"内河航运建设单位工程预算中其他直接费包括（ ）。",[116,118,120,122,124],{"key":20,"text":117,"correct":22},"冬、雨期施工增加费；夜间施工增加费",{"key":24,"text":119,"correct":22},"材料二次倒运费",{"key":27,"text":121,"correct":22},"施工队伍进退场费（调遣费）",{"key":30,"text":123,"correct":32},"浚前扫床费",{"key":34,"text":125,"correct":32},"外海工程拖船费",{"id":127,"libraryId":5,"type":15,"typeLabel":16,"stem":128,"options":129,"answer":136,"analysis":37},1130351,"内河航运建设项目总概算的组成包括（ ）。",[130,131,132,133,135],{"key":20,"text":87,"correct":22},{"key":24,"text":89,"correct":22},{"key":27,"text":91,"correct":22},{"key":30,"text":134,"correct":32},"企业利润",{"key":34,"text":93,"correct":22},"ABCE",{"id":138,"libraryId":5,"type":15,"typeLabel":16,"stem":139,"options":140,"answer":149,"analysis":37},1130352,"内河航运工程单位工程概预算费用中现场经费包括（ ）。",[141,143,145,146,148],{"key":20,"text":142,"correct":32},"施工队进退场费",{"key":24,"text":144,"correct":22},"临时设施费",{"key":27,"text":60,"correct":32},{"key":30,"text":147,"correct":22},"管理费",{"key":34,"text":62,"correct":32},"BD",{"id":151,"libraryId":5,"type":15,"typeLabel":16,"stem":152,"options":153,"answer":164,"analysis":37},1130358,"工程索赔中工程环境的变化包括（ ）。",[154,156,158,160,162],{"key":20,"text":155,"correct":22},"地质条件的变化",{"key":24,"text":157,"correct":22},"国家政策的变化",{"key":27,"text":159,"correct":32},"设计文件的改变",{"key":30,"text":161,"correct":32},"征地、拆迁的干扰",{"key":34,"text":163,"correct":32},"前项合同工程承包商的推迟","AB",{"id":166,"libraryId":5,"type":15,"typeLabel":16,"stem":167,"options":168,"answer":179,"analysis":37},1130369,"工程施工进度计划的实施包括（ ）。",[169,171,173,175,177],{"key":20,"text":170,"correct":22},"总进度计划目标的分解",{"key":24,"text":172,"correct":32},"绘制施工进度计划图",{"key":27,"text":174,"correct":22},"组织资源供应",{"key":30,"text":176,"correct":22},"落实承包责任制",{"key":34,"text":178,"correct":22},"落实施工条件","ACDE",{"id":181,"libraryId":5,"type":15,"typeLabel":16,"stem":182,"options":183,"answer":194,"analysis":37},1130389,"潜水员水下安装的作业安全规定有（ ）。",[184,186,188,190,192],{"key":20,"text":185,"correct":22},"构件基本就位和稳定后，潜水员方可靠近待安装构件",{"key":24,"text":187,"correct":22},"潜水员不得站在两构件间操作，供气管也不得置于构件缝中",{"key":27,"text":189,"correct":32},"流速较大时，潜水员应在顺流方向操作",{"key":30,"text":191,"correct":22},"构件安装应使用专用工具调整构件的安装位置",{"key":34,"text":193,"correct":22},"潜水员不得将身体的任何部位置于两构件之间","ABDE",{"id":196,"libraryId":5,"type":15,"typeLabel":16,"stem":197,"options":198,"answer":209,"analysis":37},1130396,"疏浚工程定额中的“万方艘班数”是指在（ ）条件下需要的船舶艘班数。",[199,201,203,205,207],{"key":20,"text":200,"correct":22},"标准配套的船舶",{"key":24,"text":202,"correct":32},"五级工况",{"key":27,"text":204,"correct":22},"一定的土质、泥土距离",{"key":30,"text":206,"correct":22},"挖10000方土",{"key":34,"text":208,"correct":32},"中等熟练的船员","ACD",{"id":211,"libraryId":5,"type":15,"typeLabel":16,"stem":212,"options":213,"answer":224,"analysis":37},1130400,"斜坡堤混凝土护面块体目前常用的有（ ）。",[214,216,218,220,222],{"key":20,"text":215,"correct":22},"栅栏板",{"key":24,"text":217,"correct":22},"四脚空心方块",{"key":27,"text":219,"correct":32},"半圆体",{"key":30,"text":221,"correct":22},"扭王字体",{"key":34,"text":223,"correct":32},"护面盖板","ABD",{"id":226,"libraryId":5,"type":15,"typeLabel":16,"stem":227,"options":228,"answer":194,"analysis":37},1130401,"板桩码头的结构形式应根据（ ）等因素，通过技术经济比较选定。",[229,231,233,235,237],{"key":20,"text":230,"correct":22},"自然条件",{"key":24,"text":232,"correct":22},"使用要求",{"key":27,"text":234,"correct":32},"人文环境",{"key":30,"text":236,"correct":22},"施工条件",{"key":34,"text":238,"correct":22},"工期要求",{"id":240,"libraryId":5,"type":15,"typeLabel":16,"stem":241,"options":242,"answer":253,"analysis":37},1130402,"板桩码头中的锚碇叉桩由一对叉桩和其上端现浇桩帽组成，叉桩靠（）来承受拉杆的拉力。",[243,245,247,249,251],{"key":20,"text":244,"correct":32},"桩在土中的弹性嵌固作用",{"key":24,"text":246,"correct":32},"桩前面的土体抗力",{"key":27,"text":248,"correct":22},"前压斜桩轴向力的水平分力",{"key":30,"text":250,"correct":22},"后拉斜桩轴向力的水平分力",{"key":34,"text":252,"correct":22},"前后斜桩水平分力之和","CDE",{"id":255,"libraryId":5,"type":15,"typeLabel":16,"stem":256,"options":257,"answer":224,"analysis":37},1130403,"斜坡堤堤身采用水上抛填块石施工工艺时，应根据抛填区域（）对块石产生漂流的影响，确定抛石船的驻位。",[258,260,262,264,266],{"key":20,"text":259,"correct":22},"水深",{"key":24,"text":261,"correct":22},"水流",{"key":27,"text":263,"correct":32},"风力",{"key":30,"text":265,"correct":22},"波浪",{"key":34,"text":267,"correct":32},"地质",{"id":269,"libraryId":5,"type":15,"typeLabel":16,"stem":270,"options":271,"answer":111,"analysis":37},1130404,"当采用排淤法处理软土地基时，对施工期置换淤泥质软基的平面位置及深度检查可选用的方法有（）。",[272,274,276,278,280],{"key":20,"text":273,"correct":22},"体积平衡法",{"key":24,"text":275,"correct":32},"核子密度仪法",{"key":27,"text":277,"correct":22},"钻孔探摸法",{"key":30,"text":279,"correct":32},"标准贯入法",{"key":34,"text":281,"correct":22},"探地雷达法",{"id":283,"libraryId":5,"type":15,"typeLabel":16,"stem":284,"options":285,"answer":164,"analysis":37},1130405,"重力式码头基槽挖泥时要（ ），以保证基槽平面位置准确防止欠挖和超挖。",[286,288,290,292,294],{"key":20,"text":287,"correct":22},"勤对标",{"key":24,"text":289,"correct":22},"勤测水深",{"key":27,"text":291,"correct":32},"复测断面",{"key":30,"text":293,"correct":32},"核对土质",{"key":34,"text":295,"correct":32},"复测密度",{"id":297,"libraryId":5,"type":15,"typeLabel":16,"stem":298,"options":299,"answer":164,"analysis":37},1130406,"爆破夯实是在水下块石或砾石地基和基础表面布置（ ）药包，利用水下爆破产生的地基和基础振动使地基和基础得到密实的方法。",[300,302,304,306,308],{"key":20,"text":301,"correct":22},"裸露",{"key":24,"text":303,"correct":22},"悬浮",{"key":27,"text":305,"correct":32},"密封",{"key":30,"text":307,"correct":32},"漂浮",{"key":34,"text":309,"correct":32},"基面",{"id":311,"libraryId":5,"type":15,"typeLabel":16,"stem":312,"options":313,"answer":324,"analysis":37},1130407,"重力式码头的墙体结构形式有混凝土及钢筋混凝土方块、沉箱、扶壁和大直径圆筒等，其一般施工程序包括（ ）。",[314,316,318,320,322],{"key":20,"text":315,"correct":32},"基床清淤",{"key":24,"text":317,"correct":22},"墙体预制",{"key":27,"text":319,"correct":22},"墙体预制件出运",{"key":30,"text":321,"correct":22},"墙体预制件安装",{"key":34,"text":323,"correct":32},"墙体预制件吊安","BCD",{"id":326,"libraryId":5,"type":15,"typeLabel":16,"stem":327,"options":328,"answer":339,"analysis":37},1130408,"埋放在混凝土中的块石，埋放前应冲洗干净并保持湿润。块石与块石间的净距不得小于（ ）。",[329,331,333,335,337],{"key":20,"text":330,"correct":22},"100mm",{"key":24,"text":332,"correct":32},"200mm",{"key":27,"text":334,"correct":32},"块石最小边长的1／2",{"key":30,"text":336,"correct":32},"振动棒直径的2倍",{"key":34,"text":338,"correct":22},"混凝土粗骨料最大粒径的2倍","AE",{"id":341,"libraryId":5,"type":15,"typeLabel":16,"stem":342,"options":343,"answer":52,"analysis":37},1130409,"对于高大混凝土构件，为防止混凝土松顶，浇筑至顶部时，宜采用（ ），如有泌水现象，应予排除。",[344,346,348,350,352],{"key":20,"text":345,"correct":22},"二次振捣",{"key":24,"text":347,"correct":22},"二次抹面",{"key":27,"text":349,"correct":32},"重复振捣",{"key":30,"text":351,"correct":32},"喷洒缓凝剂",{"key":34,"text":353,"correct":22},"分层减水",{"id":355,"libraryId":5,"type":15,"typeLabel":16,"stem":356,"options":357,"answer":368,"analysis":37},1130410,"海上大气区、浪溅区、水位变动区的钢筋混凝土预制构件和预应力混凝土采用淡水养护确有困难时（ ），并在浇筑2d后拆模，再喷涂蜡乳型养护剂养护。",[358,360,362,364,366],{"key":20,"text":359,"correct":32},"可用海水养护",{"key":24,"text":361,"correct":22},"南方地区可掺入适量阻锈剂",{"key":27,"text":363,"correct":32},"北方地区可掺入适量阻锈剂",{"key":30,"text":365,"correct":32},"南方地区应适当降低水灰比",{"key":34,"text":367,"correct":22},"北方地区应适当降低水灰比","BE",{"id":370,"libraryId":5,"type":15,"typeLabel":16,"stem":371,"options":372,"answer":36,"analysis":37},1130411,"重力式方块码头建筑物，方块安装时，在立面上，有（ ）安装三种方法。",[373,375,377,379,381],{"key":20,"text":374,"correct":22},"阶梯状安装",{"key":24,"text":376,"correct":22},"分段分层安装",{"key":27,"text":378,"correct":22},"长段分层安装",{"key":30,"text":380,"correct":32},"垂直分层安装",{"key":34,"text":382,"correct":32},"水平、垂直混合安装",{"id":384,"libraryId":5,"type":15,"typeLabel":16,"stem":385,"options":386,"answer":164,"analysis":37},1130412,"重力式码头沉箱接高方式一般有（ ）。",[387,389,391,393,395],{"key":20,"text":388,"correct":22},"座底接高",{"key":24,"text":390,"correct":22},"漂浮接高",{"key":27,"text":392,"correct":32},"现场接高",{"key":30,"text":394,"correct":32},"台式接高",{"key":34,"text":396,"correct":32},"移动接高",{"id":398,"libraryId":5,"type":15,"typeLabel":16,"stem":399,"options":400,"answer":164,"analysis":37},1130413,"重力式码头胸墙混凝土施工缝的形式应做成（ ）。",[401,403,405,407,409],{"key":20,"text":402,"correct":22},"垂直缝",{"key":24,"text":404,"correct":22},"水平缝",{"key":27,"text":406,"correct":32},"向岸侧倾斜缝",{"key":30,"text":408,"correct":32},"向海侧倾斜缝",{"key":34,"text":410,"correct":32},"向一端倾斜缝",{"id":412,"libraryId":5,"type":15,"typeLabel":16,"stem":413,"options":414,"answer":149,"analysis":37},1130414,"高桩码头主要由下列几部分组成：（ ）。",[415,417,419,421,423],{"key":20,"text":416,"correct":32},"墙身结构",{"key":24,"text":418,"correct":22},"基桩",{"key":27,"text":420,"correct":32},"预制构件",{"key":30,"text":422,"correct":22},"上部结构",{"key":34,"text":424,"correct":32},"混凝土面层",{"id":426,"libraryId":5,"type":15,"typeLabel":16,"stem":427,"options":428,"answer":81,"analysis":37},1130415,"高桩码头沉桩施工中，桩尖在（ ）时，以贯入度控制为主，标高作校核。",[429,431,433,435,437],{"key":20,"text":430,"correct":22},"砂性土层",{"key":24,"text":432,"correct":32},"黏性土",{"key":27,"text":434,"correct":22},"风化岩层",{"key":30,"text":436,"correct":32},"淤泥土",{"key":34,"text":438,"correct":32},"浮泥土",{"id":440,"libraryId":5,"type":15,"typeLabel":16,"stem":441,"options":442,"answer":453,"analysis":37},1130416,"驳船装运预制构件时，应注意甲板的强度和船体的稳定性，宜采用（ ）装驳。",[443,445,447,449,451],{"key":20,"text":444,"correct":32},"连续式",{"key":24,"text":446,"correct":32},"按序排列式",{"key":27,"text":448,"correct":32},"间隔式",{"key":30,"text":450,"correct":22},"宝塔式",{"key":34,"text":452,"correct":22},"对称的间隔方法","DE",{"id":455,"libraryId":5,"type":15,"typeLabel":16,"stem":456,"options":457,"answer":224,"analysis":37},1130417,"码头施工区挖泥应按下列要求进行：（ ）。",[458,460,462,464,466],{"key":20,"text":459,"correct":22},"挖泥前，测量挖泥区水深断面",{"key":24,"text":461,"correct":22},"按设计或施工要求进行阶梯形分层开挖",{"key":27,"text":463,"correct":32},"按设计或施工要求进行逐层开挖",{"key":30,"text":465,"correct":22},"挖泥完毕后，复测开挖范围的水深断面是否符合要求",{"key":34,"text":467,"correct":32},"挖泥施工中，勤测挖泥区水深断面",{"id":469,"libraryId":5,"type":15,"typeLabel":16,"stem":470,"options":471,"answer":209,"analysis":37},1130418,"接岸工程采用深层水泥搅拌加固地基时，对现场水质进行调查。查明（ ）污染程度和原因以及对水泥搅拌体的侵蚀性等。",[472,474,476,478,480],{"key":20,"text":473,"correct":22},"pH值",{"key":24,"text":475,"correct":32},"氢氧化钙",{"key":27,"text":477,"correct":22},"易溶盐",{"key":30,"text":479,"correct":22},"海水",{"key":34,"text":481,"correct":32},"碳酸钙",{"id":483,"libraryId":5,"type":15,"typeLabel":16,"stem":484,"options":485,"answer":209,"analysis":37},1130419,"板桩码头建筑物的优点是（ ）等。",[486,488,490,492,494],{"key":20,"text":487,"correct":22},"结构简单",{"key":24,"text":489,"correct":32},"板桩抗弯能力小",{"key":27,"text":491,"correct":22},"工程造价低",{"key":30,"text":493,"correct":22},"施工方便",{"key":34,"text":495,"correct":32},"适合地质广泛",{"id":497,"libraryId":5,"type":15,"typeLabel":16,"stem":498,"options":499,"answer":164,"analysis":37},1130420,"板桩建筑物沉桩时，沿板桩墙纵轴线方向的垂直度偏差超过规定时，对于钢筋混凝土板桩，可采用（ ）的方法进行调整。",[500,502,504,506,508],{"key":20,"text":501,"correct":22},"修凿桩尖斜度",{"key":24,"text":503,"correct":22},"加楔形板桩",{"key":27,"text":505,"correct":32},"调整打桩架的侧向斜度",{"key":30,"text":507,"correct":32},"现场浇筑",{"key":34,"text":509,"correct":32},"调整导向架",{"id":511,"libraryId":5,"type":15,"typeLabel":16,"stem":512,"options":513,"answer":524,"analysis":37},1130421,"板桩建筑物锚碇系统的拉杆要承受拉力，采用钢拉杆时，材料应具有出厂合格证书，并按有关规定抽样对其（ ）进行检验。",[514,516,518,520,522],{"key":20,"text":515,"correct":32},"物理性能",{"key":24,"text":517,"correct":32},"力学性能",{"key":27,"text":519,"correct":22},"机械性能",{"key":30,"text":521,"correct":22},"化学成分",{"key":34,"text":523,"correct":32},"化学性能","CD",{"id":526,"libraryId":5,"type":15,"typeLabel":16,"stem":527,"options":528,"answer":524,"analysis":37},1130422,"在斜坡堤施工中，对砂垫层的（ ）等规定了其质量要求。",[529,531,533,535,537],{"key":20,"text":530,"correct":32},"顶面曲度",{"key":24,"text":532,"correct":32},"顶面坡度",{"key":27,"text":534,"correct":22},"顶面宽度",{"key":30,"text":536,"correct":22},"顶面标高",{"key":34,"text":538,"correct":32},"顶面高度",{"id":540,"libraryId":5,"type":15,"typeLabel":16,"stem":541,"options":542,"answer":524,"analysis":37},1130423,"土工织物铺设块的拼缝宜采用（ ）连接，但在长度方向（主要受力方向）不得有接头缝。",[543,545,547,549,551],{"key":20,"text":544,"correct":32},"顺缝",{"key":24,"text":546,"correct":32},"直缝",{"key":27,"text":548,"correct":22},"丁缝",{"key":30,"text":550,"correct":22},"包缝",{"key":34,"text":552,"correct":32},"线缝",{"id":554,"libraryId":5,"type":15,"typeLabel":16,"stem":555,"options":556,"answer":253,"analysis":37},1130424,"斜坡堤堤心石抛填，当采用陆上推进法时，堤根的浅水区可一次抛填到顶，堤身和堤头视（ ）影响程度可一次或多次抛填到顶。",[557,559,561,562,564],{"key":20,"text":558,"correct":32},"流速",{"key":24,"text":560,"correct":32},"风速",{"key":27,"text":259,"correct":22},{"key":30,"text":563,"correct":22},"地基土的强度",{"key":34,"text":265,"correct":22},{"id":566,"libraryId":5,"type":15,"typeLabel":16,"stem":567,"options":568,"answer":52,"analysis":37},1130425,"斜坡堤置换淤泥质软基的平面位置及深度的检查，可选用以下检查方法：（ ），当采用其他方法时需进行论证。",[569,570,571,573,575],{"key":20,"text":273,"correct":22},{"key":24,"text":277,"correct":22},{"key":27,"text":572,"correct":32},"探地触摸法",{"key":30,"text":574,"correct":32},"体积测量法",{"key":34,"text":281,"correct":22},{"id":577,"libraryId":5,"type":15,"typeLabel":16,"stem":578,"options":579,"answer":194,"analysis":37},1130426,"斜坡堤在安装护面块体前，应对堤身以下项目进行检查：（ ），不符合要求时，应进行修整。",[580,582,584,586,588],{"key":20,"text":581,"correct":22},"块石垫层厚度",{"key":24,"text":583,"correct":22},"块石重量",{"key":27,"text":585,"correct":32},"块体重量",{"key":30,"text":587,"correct":22},"坡度",{"key":34,"text":589,"correct":22},"表面平整度",{"id":591,"libraryId":5,"type":15,"typeLabel":16,"stem":592,"options":593,"answer":96,"analysis":37},1130427,"整治沙质过渡段浅滩可采取的方法有（ ）等。",[594,596,598,600,602],{"key":20,"text":595,"correct":22},"调整航道流速",{"key":24,"text":597,"correct":22},"加高边滩",{"key":27,"text":599,"correct":22},"集中水流冲刷航槽",{"key":30,"text":601,"correct":22},"固定边滩",{"key":34,"text":603,"correct":32},"减小汇流角",{"id":605,"libraryId":5,"type":15,"typeLabel":16,"stem":606,"options":607,"answer":209,"analysis":37},1130428,"整治沙质散乱浅滩可采取的方法有（ ）等。",[608,610,611,613,615],{"key":20,"text":609,"correct":22},"固滩",{"key":24,"text":597,"correct":32},{"key":27,"text":612,"correct":22},"筑坝",{"key":30,"text":614,"correct":22},"护岸",{"key":34,"text":616,"correct":32},"增大浅区冲刷能力",{"id":618,"libraryId":5,"type":15,"typeLabel":16,"stem":619,"options":620,"answer":36,"analysis":37},1130429,"整治卵石弯道浅滩可采取的方法有（ ）等。",[621,623,625,627,629],{"key":20,"text":622,"correct":22},"在凹岸建顺坝",{"key":24,"text":624,"correct":22},"在凹岸建下挑丁坝",{"key":27,"text":626,"correct":22},"疏浚凸岸浅区",{"key":30,"text":628,"correct":32},"建洲头顺坝",{"key":34,"text":630,"correct":32},"建潜坝",{"id":632,"libraryId":5,"type":15,"typeLabel":16,"stem":633,"options":634,"answer":96,"analysis":37},1130430,"土工织物软体排护底沉排时应及时调整船位、控制沉排方向和沉排速度，排体应（ ）。",[635,637,639,641,643],{"key":20,"text":636,"correct":22},"平顺入水",{"key":24,"text":638,"correct":22},"松紧适度",{"key":27,"text":640,"correct":22},"与水深相适应",{"key":30,"text":642,"correct":22},"与河床地形相适应",{"key":34,"text":644,"correct":32},"与流向一致",{"id":646,"libraryId":5,"type":15,"typeLabel":16,"stem":647,"options":648,"answer":149,"analysis":37},1130431,"钢丝网石笼垫的填充石料宜选用卵石；其（ ）应满足设计要求。",[649,651,653,655,657],{"key":20,"text":650,"correct":32},"形状",{"key":24,"text":652,"correct":22},"粒径",{"key":27,"text":654,"correct":32},"磨圆度",{"key":30,"text":656,"correct":22},"级配",{"key":34,"text":658,"correct":32},"风化程度",{"id":660,"libraryId":5,"type":15,"typeLabel":16,"stem":661,"options":662,"answer":209,"analysis":37},1130432,"砂枕坝体施工前，应根据（ ）等绘制坝体断面砂枕布置图。",[663,665,667,669,671],{"key":20,"text":664,"correct":22},"河床地形",{"key":24,"text":666,"correct":32},"冲刷情况",{"key":27,"text":668,"correct":22},"坝体设计高程",{"key":30,"text":670,"correct":22},"坝体设计坡比",{"key":34,"text":672,"correct":32},"地基承载力",{"id":674,"libraryId":5,"type":15,"typeLabel":16,"stem":675,"options":676,"answer":687,"analysis":37},1130433,"砂枕坝体抛筑时应检测（ ）等，并随时根据断面尺寸合理搭配不同长度的砂枕。",[677,679,681,683,685],{"key":20,"text":678,"correct":32},"坝体稳定性",{"key":24,"text":680,"correct":32},"砂枕漂移距",{"key":27,"text":682,"correct":22},"坝体高度",{"key":30,"text":684,"correct":32},"砂枕充填度",{"key":34,"text":686,"correct":22},"坝体边坡","CE",{"id":689,"libraryId":5,"type":15,"typeLabel":16,"stem":690,"options":691,"answer":702,"analysis":37},1130434,"石笼坝体抛筑过程中，应随时检查（ ）等，坡度不得陡于设计坡比。",[692,694,696,698,700],{"key":20,"text":693,"correct":22},"坝位",{"key":24,"text":695,"correct":32},"绞合间距",{"key":27,"text":697,"correct":32},"充填度",{"key":30,"text":699,"correct":22},"坝身",{"key":34,"text":701,"correct":22},"边坡","ADE",{"id":704,"libraryId":5,"type":15,"typeLabel":16,"stem":705,"options":706,"answer":66,"analysis":37},1130435,"关于现浇混凝土镶嵌卵石坝面施工的说法，错误的是（ ）。",[707,709,711,713,715],{"key":20,"text":708,"correct":32},"嵌入深度宜为卵石长度的3／4",{"key":24,"text":710,"correct":22},"卵石间距宜为10mm",{"key":27,"text":712,"correct":22},"两边卵石距坝体轮廓边线应不小于20mm",{"key":30,"text":714,"correct":32},"卵石顶面高程应满足设计要求",{"key":34,"text":716,"correct":32},"顶高宜比混凝土面高20～30mm",{"id":718,"libraryId":5,"type":15,"typeLabel":16,"stem":719,"options":720,"answer":324,"analysis":37},1130436,"下列关于浆砌块石护面施工的说法，正确的有（ ）。",[721,723,725,727,729],{"key":20,"text":722,"correct":32},"勾缝砂浆标号应不低于砌体砂浆",{"key":24,"text":724,"correct":22},"砂浆应分层填实",{"key":27,"text":726,"correct":22},"应自下而上进行，分段砌筑",{"key":30,"text":728,"correct":22},"砌筑时不得先堆砌块石再用砂浆灌缝",{"key":34,"text":730,"correct":32},"护面施工前应检查护脚的质量",[732,736,739,742,745,748],{"id":733,"name":734,"category":7,"favorite":735},1,"领导干部任职前廉政法规知识测试题",92,{"id":737,"name":738,"category":7,"favorite":733},595,"建筑结构与设备",{"id":740,"name":741,"category":7,"favorite":733},715,"招标采购专业知识与法律法规",{"id":743,"name":744,"category":7,"favorite":733},848,"市政方向-通用基础",{"id":746,"name":747,"category":7,"favorite":8},534,"BIM工程师",{"id":749,"name":747,"category":7,"favorite":8},535]