[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130718":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130718,794,2,"多选题","疏浚工程定额中，自然影响包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","风",true,{"key":16,"text":17,"correct":18},"B","船舶避让",false,{"key":20,"text":21,"correct":14},"C","雾",{"key":23,"text":24,"correct":14},"D","浪",{"key":26,"text":27,"correct":18},"E","停电","ACD","自然影响时间:指受风、雾、雨、浪、潮汐、水位和流速的影响而不能施工的时间。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]