[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130693":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130693,794,2,"多选题","港航工程中实际进度与计划进度相比较常用的方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","横道图比较法",true,{"key":16,"text":17,"correct":14},"B","列表比较法",{"key":19,"text":20,"correct":21},"C","产值效益比较法",false,{"key":23,"text":24,"correct":21},"D","资金周转率比较法",{"key":26,"text":27,"correct":14},"E","前锋线网络计划比较法","ABE","2020版教材页码P321-P323 港航工程中实际进度与计划进度常用的分析比较方法有以下几种: （1）横道图的比较法； （2）列表比较法； （3）前锋线网络计划分析法。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]