[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130692":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130692,794,2,"多选题","检查工程进度计划完成情况常用的统计方法有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程形象进度统计法",true,{"key":16,"text":17,"correct":14},"B","实物工程量统计法",{"key":19,"text":20,"correct":14},"C","施工产值统计法",{"key":22,"text":23,"correct":24},"D","投入产出比统计法",false,{"key":26,"text":27,"correct":24},"E","劳动生产率统计法","ABC","2020版教材页码P321-P323 进度统计是计划控制、分析、调整的基础和根本： 1.工程形象进度的统计 2.实物工程量'统计 3.施工产值的统计",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]