[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130691":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130691,794,2,"多选题","施工总进度计划的编制依据包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目的工程承包合同",true,{"key":16,"text":17,"correct":14},"B","项目的施工组织设计",{"key":19,"text":20,"correct":14},"C","设计的进度计划",{"key":22,"text":23,"correct":24},"D","企业的效益情况",false,{"key":26,"text":27,"correct":24},"E","政府的监督意见","ABC","2020版教材页码P317-P319 施工总进度计划的编制依据： 1. 项目的工程承包合同 2. 项目的施工组织设计 3. 设计的进度计划",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]