[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130690":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130690,794,2,"多选题","对施工进度计划的内容检查后，应提出月度施工进度报告，报告应包括下列内容（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进度执行情况的综合叙述",true,{"key":16,"text":17,"correct":18},"B","向监理工程师提出报告",false,{"key":20,"text":21,"correct":14},"C","进度偏差及原因分析",{"key":23,"text":24,"correct":14},"D","解决问题的措施及计划调整意见",{"key":26,"text":27,"correct":14},"E","实际的施工进度图","ACDE","2020版教材页码P319-P321 进度管理情况及进度偏差情况，影响进度的特殊原因及分析。检查后，应提出月度施工进度报告，报告应包括下列内容: （1）进度执行情况的综合叙述及实际的施工进度图，进度偏差的状况及其原因分析。 （2）工程变更、价格调整、索赔及工程款收支情况。 （3）解决问题的措施及计划调整意见。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]