[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130687":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130687,794,2,"多选题","单位工程施工进度计划的编制依据包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目管理目标责任书",true,{"key":16,"text":17,"correct":14},"B","施工总进度计划",{"key":19,"text":20,"correct":14},"C","施工方案",{"key":22,"text":23,"correct":24},"D","总监理工程师随时提出的意见",false,{"key":26,"text":27,"correct":14},"E","施工现场的平均可工作天数","ABCE","2020版教材页码P317-P319 单位工程施工进度计划的编制制依据“项目管理目标责任书”；施工总进度计划;施工方案;主要材料和设备的供应能力;施工人员的技术素质及劳动效率;施工现场条件， （气候、环境、海况等）平均可工作天数;已建成的同类工程的实际进度及经济指标等。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]