[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130686":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130686,794,2,"多选题","施工总进度计划的内容应包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","编制说明",true,{"key":16,"text":17,"correct":14},"B","施工总进度计划表",{"key":19,"text":20,"correct":14},"C","分批施工工程的开工日期一览表",{"key":22,"text":23,"correct":24},"D","效益量化指标",false,{"key":26,"text":27,"correct":14},"E","资源需求量及供应平衡表","ABCE","2020版教材页码P317-P319 施工总进度计划的内容:应包括编制说明;施工总进度计划表;分期、分批施工工程的开工日期、完工日期及工期一览表;资源需求量及供应平衡表等。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]