[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130685":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130685,794,2,"多选题","项目进度目标可以按（ ）进行分解。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","单位工程",true,{"key":16,"text":17,"correct":14},"B","施工阶段",{"key":19,"text":20,"correct":14},"C","承包专业",{"key":22,"text":23,"correct":14},"D","年、季、月进度计划",{"key":25,"text":26,"correct":27},"E","经济效益高低",false,"ABCD","2020版教材页码P317-P319 项目进度控制总目标应进行分解。以便按单位工程或者按施工阶段、按专业、按节点制定更具体、更落实、更有保证的措施，加强进度控制，以分解后各局部项目、阶段的进度控制，保证项目进度总目标的实现。项目进度控制总目标可以按以下原则进行分解: （1）按单位工程分解为交工分目标。 （2）按承包的专业或施工阶段分解为各完工的分目标。 （3）按年、季、月进度计划，分解为时间分目标。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]