[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130684":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130684,794,2,"多选题","索赔事件主要包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人违约",true,{"key":16,"text":17,"correct":18},"B","工程量增加",false,{"key":20,"text":21,"correct":18},"C","设计方案改变",{"key":23,"text":24,"correct":14},"D","不可抗力因素",{"key":26,"text":27,"correct":14},"E","第三人造成的违约","ADE","2020版教材页码P313-P315 索赔事件主要包括: 1.发包人违约。 2. 不可抗力因素。 3. 第三人造成的违约。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]