[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130683":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130683,794,2,"多选题","出现（ ）的情况时，施工单位延期申请能够成立并获得监理工程师批准。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","延期是由施工单位自身原因引起",false,{"key":16,"text":17,"correct":18},"B","建设单位原因造成工程延误",true,{"key":20,"text":21,"correct":18},"C","设计变更或工程量增加造成工程延误",{"key":23,"text":24,"correct":18},"D","不可抗力或地质条件变化造成工程延误",{"key":26,"text":27,"correct":18},"E","合同专用条款中约定的其他","BCDE","2020版教材页码P313-P315 港口与航道工程施工周期长，受各种工况条件影响多，实施过程中往往会有各种各样的索赔事件发生， 索赔事件主要包括: 1. 发包人违约。 2. 不可抗力因素。 3. 第三人造成的违约。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]