[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130681":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130681,794,2,"多选题","在施工过程中，导致暂停施工可以进行工期索赔的情况有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","非施工单位原因，建设单位代表要求暂停施工",true,{"key":16,"text":17,"correct":18},"B","非建设单位原因，施工单位要求暂停施工",false,{"key":20,"text":21,"correct":14},"C","由于建设单位违约，承包方主动暂停施工",{"key":23,"text":24,"correct":18},"D","由于施工单位违约，发包方要求暂停施工",{"key":26,"text":27,"correct":18},"E","施工单位新技术应用","AC","2020版教材页码P313-P315 工期索赔需要是非施工方自身原因引起的工期延误。ＡＣ均属于非施工方原因。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]