[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130676":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130676,794,2,"多选题","港口工程施工合同规定，属于（ ）的情况，承包商可以获得工程延期。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位延误施工现场移交",true,{"key":16,"text":17,"correct":18},"B","施工单位施工设备出现故障",false,{"key":20,"text":21,"correct":14},"C","工程师延误图纸移交",{"key":23,"text":24,"correct":18},"D","不利于施工的自然条件和障碍影响",{"key":26,"text":27,"correct":18},"E","暂时停工","AC","2020版教材页码P313-P315 在履行合同过程中发生的下列情形，属发包人违约: （1）发包人未能按合同约定支付预付款或合同价款，或拖延、拒绝批准付款申请和支付凭证，导致付款延误的。 （2）发包人原因造成停工的。 （3）监理人无正当理由没有在约定期限内发出复工指示，导致承包人无法复工的。 （4）发包人无法继续履行或明确表示不履行或实质上已停止履行合同的。 （5）发包人不履行合同约定其他义务的。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]