[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130673,794,2,"多选题","工程费用应由（ ）等组成。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","直接费",false,{"key":16,"text":17,"correct":14},"B","间接费",{"key":19,"text":20,"correct":21},"C","建筑工程费",true,{"key":23,"text":24,"correct":21},"D","设备购置费",{"key":26,"text":27,"correct":21},"E","安装工程费","CDE","2020版教材页码P309-P311 工程费用应由建筑工程费、设备购置费、安装工程费等组成，并应符合下列规定。 （1）建筑工程费、安装工程费应由定额直接费、其他直接费、企业管理费、利润、规费、增值税和专项税费组成。 （2）设备购置费应由设备原价、运杂费等费用组成。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]