[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130669":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130669,794,2,"多选题","航道整治工程施工组织设计中应编制施工进度计划，其内容应包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工总进度计划和施工总进度保证措施",true,{"key":16,"text":17,"correct":14},"B","主要分部（项）工程施工网络计划及说明",{"key":19,"text":20,"correct":21},"C","施工劳动力需求量计划及说明",false,{"key":23,"text":24,"correct":21},"D","施工准备工作计划及说明",{"key":26,"text":27,"correct":14},"E","单位工程施工进度计划图及说明","ABE","2020版教材页码P298-P304 施工进度计划：包括施工总进度计划和施工总进度保证措施，单位工程施工进度计划图及其说明，主要分部（项）工程施工网络计划及其说明，施工进度控制措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]