[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130667":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130667,794,2,"多选题","航道整治工程施工部署的内容和侧重点在航道整治工程施工中一般应包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","确定总体施工程序",true,{"key":16,"text":17,"correct":14},"B","划分项目施工阶段界线",{"key":19,"text":20,"correct":21},"C","企业生产经营能力",false,{"key":23,"text":24,"correct":14},"D","确定工程施工总进度安排及主要项目程序",{"key":26,"text":27,"correct":14},"E","根据交工期限要求确定各单项工程竣工时间","ABDE","2020版教材页码P298-P304 施工的总体部署:明确项目管理组织体系及各承包单位的施工项目，确定总体施工程序或施工顺序及分期或分阶段实施的工程项目内容，工程施工总进度安排及主要项目程序，并对主要控制工期作必要的说明，划分项目施工阶段界线，确定分期交工的项目组成，并根据交工期限要求确定各单项工程竣工时间。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]