[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130662":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130662,794,2,"多选题","编制施工计划时，疏浚工程施工进度应包括（ ）三个阶段。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","现场准备",true,{"key":16,"text":17,"correct":14},"B","施工",{"key":19,"text":20,"correct":14},"C","竣工验收",{"key":22,"text":23,"correct":24},"D","浚前测量",false,{"key":26,"text":27,"correct":24},"E","浚后测量","ABC","2020版教材页码P295-P298 疏浚工程进度应包括现场准备、施工和竣工验收三个阶段。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]