[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130660":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130660,794,2,"多选题","高桩码头工程施工组织设计编制中，“技术经济条件”包括：预制构件加工、劳动力市场情况等建设项目地区的施工能力；钢材、木材、水泥、黄沙和石子等大宗建筑材料供应情况；交通条件和（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","机械设备租赁条件",true,{"key":16,"text":17,"correct":14},"B","水电供应条件",{"key":19,"text":20,"correct":21},"C","工程地质条件",false,{"key":23,"text":24,"correct":21},"D","水位资料",{"key":26,"text":27,"correct":21},"E","潮流资料","AB","技术经济条件 （ 1 ）建设项目地区的施工能力:预制构件加工、机械设备租赁、劳动力市场情况。 （ 2 ）资源供应情况:钢材、木材、水泥、黄沙和石子等大宗建筑材料供应情况。 （ 3 ）交通和水电等条件。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]