[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130655":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130655,794,2,"多选题","航道整治工程施工组织设计中的主要技术经济指标一般应包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工工期",true,{"key":16,"text":17,"correct":14},"B","施工成本",{"key":19,"text":20,"correct":14},"C","施工质量",{"key":22,"text":23,"correct":24},"D","施工条件",false,{"key":26,"text":27,"correct":14},"E","施工效率","ABCE","主要技术经济指标：包括施工工期、施工成本、施工质量、施工安全和施工效率以及其他技术经济指标。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]