[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130649":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130649,794,2,"多选题","高桩码头工程施工组织设计编制中，“沉桩施工方案”包括障碍物的探摸清除，（ ），锤、桩船（桩架）、桩垫木和替打的选用，锚缆和地笼的布设，桩的运输和堆放，斜坡上沉桩技术措施及岸坡稳定，桩的高应变和低应变动测。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定梁板安装顺序",false,{"key":16,"text":17,"correct":18},"B","编制运桩图和落驳图",true,{"key":20,"text":21,"correct":14},"C","确定制桩顺序",{"key":23,"text":24,"correct":18},"D","确定沉桩顺序",{"key":26,"text":27,"correct":14},"E","确定测量顺序","BD","2020版教材页码P286-P292 沉桩施工方案包括障碍物的探摸清除，确定沉桩顺序，编制运桩图和落驳图，锤、桩船（桩架）、桩垫木和替打的选用，锚缆和地笼的布设，桩的运输和堆放，斜坡上沉桩技术措施及岸坡稳定，桩的高应变和低应变动测。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]