[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130648":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130648,794,2,"多选题","高桩码头工程施工组织设计编制中，主要施工方案的内容有：挖泥、测量、构件预制及安装、模板工程、钢筋工程、（ ）、土石方工程、设备安装工程、附属设施安装工程等。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","混凝土工程",true,{"key":16,"text":17,"correct":14},"B","沉桩",{"key":19,"text":20,"correct":21},"C","粉刷工程",false,{"key":23,"text":24,"correct":21},"D","照明工程",{"key":26,"text":27,"correct":21},"E","砌筑工程","AB","高桩码头施工方案的主要内容有:挖泥、测量、沉桩、构件预制及安装、模板工程、钢筋工程、混凝土工程、土石方工程、设备安装工程、附属设施安装工程等。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]