[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130646":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130646,794,2,"多选题","高桩码头工程施工组织设计编制中，高桩码头施工工序主要有（ ）、现浇混凝土和岸坡施工等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","沉桩",true,{"key":16,"text":17,"correct":18},"B","测量",false,{"key":20,"text":21,"correct":14},"C","施工挖泥",{"key":23,"text":24,"correct":14},"D","构件安装",{"key":26,"text":27,"correct":18},"E","系船柱安装","ACD","2020版教材页码P286-P292 高桩码头施工工序主要有施工挖泥、沉桩、构件安装、现浇混凝土和岸坡施工等方面。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]