[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130625":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130625,794,2,"多选题","施工合同中，（ ）应由承包人完成。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","土地征用和拆迁",false,{"key":16,"text":17,"correct":18},"B","提供施工船舶的临时停泊设施",true,{"key":20,"text":21,"correct":14},"C","提供工程地质报告",{"key":23,"text":24,"correct":18},"D","保护施工现场地下管道和邻近建筑物及构筑物",{"key":26,"text":27,"correct":18},"E","提供相应的工程进度计划及统计报表","BDE","2020版教材页码P224-P229 发包人应按专用合同条款约定向承包人提供施工场地，以及施工场地内地下管线和地下设施等有关资料，并保证资料的真实、准确、完整。 （1）发包人应在计划开工日期14d前，向承包人无偿提供能满足工程主体范围井有合理有效的施工作业面位置的施工水域或场地，提供的施工水域或场地面积，应满足招标文件的最低要求。 （2）发包人应在计划开工日期14d前，提供能满足承包人生产、生活需要的临时施工水域或场地。 （3）发包人应在计划开工日期14d前，开通进出施工现场的交通通道，提供水、电、通信的接点及施工船舶临时停泊水域并保证施工期间的畅通和完好。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]