[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130584":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130584,794,2,"多选题","疏浚工程设计时计算的工程量，包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设计断面工程量",true,{"key":16,"text":17,"correct":14},"B","计算超宽量",{"key":19,"text":20,"correct":14},"C","计算超深量",{"key":22,"text":23,"correct":24},"D","施工期回淤量",false,{"key":26,"text":27,"correct":24},"E","骤淤量","ABC","2020版教材页码P235-P238 疏浚工程采用实测下方进行土方计量时，应分别计算设计断面工程量、计算超深与计算超宽工程量、根据自然条件与施工工期计入的施工期回淤工程量。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]