[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130578":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130578,794,2,"多选题","隐蔽工程在隐蔽前应（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","自检合格",true,{"key":16,"text":17,"correct":14},"B","通知有关单位验收",{"key":19,"text":20,"correct":21},"C","通知建设单位检验",false,{"key":23,"text":24,"correct":14},"D","形成验收文件",{"key":26,"text":27,"correct":21},"E","通知监理验收","ABD","2020版教材页码P386-P387 工程质量的检验应在施工单位自行检验合格的基础上进行。隐蔽工程在隐蔽前应由施工单位通知有关单位进行验收，并形成验收文件。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]