[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130558":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130558,794,2,"多选题","港口航道工程测量建立矩形施工控制网的规定包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","边长宜为100～200m",true,{"key":16,"text":17,"correct":14},"B","轴线方向与施工坐标轴线方向一致",{"key":19,"text":20,"correct":14},"C","矩形施工控制网的原点及轴线方位应与整个平面坐标系联测",{"key":22,"text":23,"correct":24},"D","边长宜为300～500m",false,{"key":26,"text":27,"correct":14},"E","矩形施工控制网轴线点位中误差不应大于50mm","ABCE","2020版教材页码P99-P101 建立矩形施工控制网应符合下列规定: （1）矩形施工控制网边应根据建筑物的规模而定，宜为100 - 200m。 （2）矩形施工控制网的轴线方向宜与施工坐标系的坐标轴方向一致，矩形施工控制网的原点及轴线方位应与整个平面坐标系联测，其轴线点点位中误差不应大于50mm 。 （3）矩形施工控制网角度闭合差不应大于测角中误差的4 倍。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]