[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130529":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130529,794,2,"多选题","工程勘察报告是勘察工作的最终成果，由（ ）构成，应满足相应设计阶段的技术要求。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计算书",false,{"key":16,"text":17,"correct":18},"B","文字",true,{"key":20,"text":21,"correct":14},"C","现场勘察工作日记",{"key":23,"text":24,"correct":18},"D","图表",{"key":26,"text":27,"correct":14},"E","勘察费用","BD","2020版教材页码P14-P25 勘察报告是勘察工作的最终成果，由文字和图表构成，应满足相应设计阶段的技术要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]