[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130518":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130518,794,2,"多选题","堆载预压工程应作好施工监测和效果检验，在堆载过程中应每天进行（ ）等的观测，并符合控制标准。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","孔隙水",true,{"key":16,"text":17,"correct":14},"B","沉降",{"key":19,"text":20,"correct":21},"C","土的强度",false,{"key":23,"text":24,"correct":21},"D","排水量",{"key":26,"text":27,"correct":14},"E","位移","ABE","2020版教材页码P76-P79 堆载预压工程在堆载过程中应每天进行沉降、位移、孔隙水等的观测，控制标准如下:边桩水平位移每昼夜应小于5mm ，基底的中心沉降每昼夜应小于10mm 。孔隙水压力系数控制在0.6 以控制施工速率。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]