[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130478":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130478,794,2,"多选题","砂枕坝体水上抛投施工过程中，应根据（ ）等的不同及时调整定位船位置。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","风力",false,{"key":16,"text":17,"correct":14},"B","波浪",{"key":19,"text":20,"correct":21},"C","流速",true,{"key":23,"text":24,"correct":21},"D","流向",{"key":26,"text":27,"correct":14},"E","潮差","CD","2020版教材页码P165-P169 砂枕水上抛投施工过程中，应适时测定施工区域的流速、流向以及砂枕的漂移距。根据流速、流向、漂移距的不同及时调整定位船位置。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]