[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130474":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130474,794,2,"多选题","黏土防渗体施工的规定有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","土的原材料应进行粉碎加工",true,{"key":16,"text":17,"correct":14},"B","防渗体基底应清理杂物并排干积水",{"key":19,"text":20,"correct":21},"C","防渗体与集水槽不宜同步施工",false,{"key":23,"text":24,"correct":14},"D","分层铺筑时，上下层接缝应错开",{"key":26,"text":27,"correct":21},"E","分段、分片施工时，相邻工作面搭接碾压宽度：平行轴线方向不应小于300mm，垂直轴线方向不应小于2m","ABD","2020版教材页码P152-P154 黏土防渗体施工应符合下列规定: （1）土的原材料应进行粉碎加工，加工后的粒径，新土不大于2mm，石灰不大于5mm。 （2）防渗体基底应清理杂物并排干积水。 （3）防渗体与集水槽宜同步施工。 （4）分层铺筑时，上下层接缝应错开，采用人工夯实时每层虚土铺筑厚度不应大于200mm，采用机械夯实时每层虚土铺筑厚度不应大于300mm，层面间应刨毛、洒水。 （5）分段、分片施工时，相邻工作面搭接碾压宽度:平行轴线方向不应小于500mm ，垂直轴线方向不应小于3m 。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]