[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130473":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130473,794,2,"多选题","停止基坑降水至少应具备的条件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","闸室结构物沉降、位移满足要求",true,{"key":16,"text":17,"correct":18},"B","闸室主体施工完成",false,{"key":20,"text":21,"correct":14},"C","闸室放水前应保持干地施工及监测条件",{"key":23,"text":24,"correct":18},"D","上下游闸门已安装完毕",{"key":26,"text":27,"correct":14},"E","结构物施工至地下水位浸润线以上","ACE","2020版教材页码P148-P149 在闸室结构物沉降、位移满足要求且结构物施工至地下水位浸润线以上后可停止降水，但闸室放水前应保持干地施工及监测条件。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]