[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130470":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130470,794,2,"多选题","高桩码头岸坡施工在沉桩后进行回填或抛石前，应先（ ）。抛填过程中，宜定时施测回淤量。清淤后应及时进行抛填，应做到随清随抛。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","测量施工区域断面",false,{"key":16,"text":17,"correct":18},"B","清除回淤浮泥",true,{"key":20,"text":21,"correct":18},"C","清除塌坡泥土",{"key":23,"text":24,"correct":14},"D","选择施工船舶",{"key":26,"text":27,"correct":14},"E","备好抛填用料","BC","2020版教材页码P134-P137 沉桩后进行回填或抛石前，先清除回淤浮泥和塌坡泥土。抛填过程中，宜定时施测回淤量。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]