[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130467":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130467,794,2,"多选题","港口与航道工程中，高桩码头混凝土预制构件在预制场存放时应符合下列规定：（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","存放场地宜平整",true,{"key":16,"text":17,"correct":14},"B","按两点或多点支垫",{"key":19,"text":20,"correct":21},"C","场地需浇筑混凝土地坪",false,{"key":23,"text":24,"correct":14},"D","不同规格的预制构件，宜分别存放",{"key":26,"text":27,"correct":21},"E","按出运次序存放","ABD","2020版教材页码P131-P133 预制构件存放符合下列规定: （1）存放场地宜平整。 （2）按两点吊设计的预制构件，可用两点支垫存放，但应避免较长时间用两点堆置，致使构件发生挠曲变形。必要时可采用多点垫或其他方式存放。按三点以上设计的预制构件，宜采用多点支垫存放。垫木应均匀铺设，并应注意场地不均匀沉降对构件的影响。 （3）不同规格的预制构件，宜分别存放。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]