[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130466":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130466,794,2,"多选题","沉桩控制应包括（ ）控制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","偏位",true,{"key":16,"text":17,"correct":18},"B","强度",false,{"key":20,"text":21,"correct":14},"C","承载力",{"key":23,"text":24,"correct":18},"D","锤击次数",{"key":26,"text":27,"correct":14},"E","裂损","ACE","2020版教材页码P126-P131 沉桩控制包括偏位控制、承载力控制和桩的裂损控制。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]