[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130465":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130465,794,2,"多选题","沉桩时要保证桩偏位不超过规定，偏位过大，会带来以下问题：（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","给上部结构预制件的安装带来困难．",true,{"key":16,"text":17,"correct":14},"B","使结构受到有害的偏心力",{"key":19,"text":20,"correct":21},"C","增加工作量",false,{"key":23,"text":24,"correct":21},"D","使工期滞后",{"key":26,"text":27,"correct":21},"E","增加施工成本","AB","2020版教材页码P126-P131 沉桩时要保证桩偏位不超过规定，偏位过大，给上部结构预制件的安装带来困难，也会使结构受到有害的偏心力。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]