[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130460":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130460,794,2,"多选题","设计方块模板与支撑系统的荷载组合中，计算强度采用（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","倾倒混凝土时产生的荷载",true,{"key":16,"text":17,"correct":18},"B","插入式振捣器产生的荷载",false,{"key":20,"text":21,"correct":14},"C","新浇混凝土对模板侧面的压力",{"key":23,"text":24,"correct":18},"D","模板上人员设备荷载",{"key":26,"text":27,"correct":18},"E","超速浇筑荷载","AC","2020版教材页码P118-P122 方块模板与支撑系统应考虑下列荷载的组合: 计算强度采用倾倒混凝土时产生的荷载和新浇混凝土对模板侧面的压力; 验算刚度采用新浇混凝土对模板侧面的压力;",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]