[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130458":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130458,794,2,"多选题","爆炸夯实施工时，夯实率检查可分别选用（ ）等方法。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","水砣",true,{"key":16,"text":17,"correct":14},"B","测杆",{"key":19,"text":20,"correct":14},"C","测深仪",{"key":22,"text":23,"correct":24},"D","测绳",false,{"key":26,"text":27,"correct":24},"E","估算","ABC","2020版教材页码P114-P118 夯实率检查可分别选用水砣、测杆、测深仪等方法。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]