[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130451":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130451,794,2,"多选题","泥层厚度过大时应分层开挖，铲斗挖泥船分层厚度应根据（ ）确定。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","斗高",true,{"key":16,"text":17,"correct":18},"B","斗容",false,{"key":20,"text":21,"correct":14},"C","土质",{"key":23,"text":24,"correct":18},"D","挖深",{"key":26,"text":27,"correct":18},"E","前移距","AC","2020版教材页码P193-P198 泥层厚度大于一次开挖的适宜厚度时应进行分层，分层厚度根据土质和斗高确定。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]